background image

PAGE 2 OF 3 

0714 IH-3504

ASSEMBlY

ROOF FRAME ASSEMBLY

1.  Start top frame assembly as shown. (See Figure 1) 

The 36" pipes are used for the roof rafters and 69" 

pipes form the length of the frame. Start assembly 

with center peak as circled. (See Figure 1)

2.  Once you have assembled the roof frame, insert the 

legs on one side using the 69" pipes with the foot 

pads installed. (See Figure 2)

3.  With the top frame on one side and the legs inserted 

on the other side (See Figure 3) drape the 1-piece 

cover with sides and rear wall over the frame. Make 

sure you have the open end in the direction 

needed. Pull 1 side down over the frame with the 

legs inserted. You can also pull the rear over the 

frame partially. Next, insert the legs on the opposite 

side and pull the rest of the cover on. (See Figure 3)

COVER ASSEMBLY

1.  With frame assembled and cover on, you can now 

attach cover to frame using the ball straps. The 

grommet holes on the cover are located along the 

back and front frame line. (See Figure 4) Attach the 

cover by running the strap through the grommet 

hole, around the pipe, then loop strap over the 

ball. If the straps are too long for a tight fit, you can 

double wrap them or make an additional knot in the 

strap cord to shorten them. 

2.  To install side rails and wall support, slide a 69" pipe 

into the sleeves at the bottom of the side walls.  

(See Figures 5) 

3.  Use double-side clamp to connect to center leg, 

and single-side clamp to connect the corner legs. 

(See Figures 6-9) 

69" Pipe

36" Pipe

Figure 1

69" Pipe

Foot Pad

Front

Side

Figure 2

Figure 3

Attach 

Ball Straps

Figure 4

Figure 5

Figure 8

Figure 6

Figure 7