6
3.3.3
Install the mounting brackets on the correct position. Respect
correct orientation.
3.3.4
Place the top cover back on the shelf.
3.3.5
Determine the position of the shelf (see rack installation
instruction). Fix the cage nuts into the
rack. Mount the shelf using the FACC-ALLEN key.
3.4
Termination of loose tube cable
3.4.1
Open the drawer to the fully open position. Strip the cable
approx 1.8m. Cut the strength member approx 100mm. Feed the cable
through the flex tube.
3.4.3
Put FOSC-400AA tray in place. Cut 4 pieces of spiral tube
200mm. Put foam at the ends of the spiral tubes.
3.4.4
Strip LT ( loose tube ) over 1.1meter starting at 170mm after
end of flex tube.
3.4.2
Fasten cable with push T-wraps and put strength member in
strength member connector. Use foam there where the cable is fixed.
3.4.5
Put foam at the end of the LT. Fasten the LT together with
spiral tube with two T-wraps. Always put the LT to the outside of the
FOSC tray. Route the primary coated fiber on the FOSC tray.
3.4.6
Fasten the second spiral tube to the FOSC-tray.
In case of 19 inch. (standard)
In case of ETSI
Termination at the back