![TurnOnGreen EVP1100 Series Скачать руководство пользователя страница 24](http://html1.mh-extra.com/html/turnongreen/evp1100-series/evp1100-series_user-manual_1182202024.webp)
Installation of the wire box
First, remove the waterproof cover at the inlet end marked as "AC In".
Then, install the accessory "1-inch liquidtight flexible metal conduit" at
the inlet of the power cord, and attach the wire box to the wall-mounted
metal plate with screws.
Installation of the AC power cord
The cross-sectional area of the three power cords should be AWG 6 or
14mm2. The power cords should be fully crimped and connected with ring
terminals. The ring terminals should be attached to the wire box with M5
screws, with a tightening torque of 40kg-cm. Please refer to label on the wire
box for the correct positions, where the positions are L1/L, GND/PE, and L2/N,
respectively, from the left to the right.
STEP 3
STEP 2
L/L1 G/PE N/L2
21
EVP1100 Series - User Manual