60
10.2016
TNX65/42
Alignment, component installation and commissioning
Transport and installation of the chip conveyor
Note the corresponding manufacturer's documentation
• Lift the chip conveyor off the pallet with a rope and set it down.
• Turn up the feet until the chip conveyor rests on the rollers.
• The two stop bolts on the bottom box must be set to 20 mm.
• Push the chip conveyor as far as possible under the machine from the
operator side.
• Raise the chip conveyor with the adjusting screws until it is horizontal and
the bottom edge of the chip conveyor is 50 mm from the floor all-round.
Setting the level switch of the chip conveyor
Note the corresponding manufacturer's documentation
The level switch on the chip conveyor is normally set to emulsion as standard
medium.
When the machine is operated with cutting oil, the level switch must be
switched over accordingly before starting.
Note the User Manual (parameter list) provided by the manufacturer.
Lubricoolant unit
Note the corresponding manufacturer's documentation
The cooling lubricant unit has to be aligned to the respective emulsion or
cutting oil medium as required.
Note the User Manual (parameter list) provided by the manufacturer.
Bar feeding mechanisms
Note the corresponding manufacturer's documentation
The bar feeding mechanisms and other accessories must be mounted,
aligned and secured to the floor as directed by the respective manufacturers.
Содержание TNX42
Страница 6: ...6 22 10 2021 TNX65 42 Table of contents...
Страница 8: ...8 10 2016 TNX65 42 Safety...
Страница 11: ...11 10 2016 TNX65 42 Installation and layout diagrams Installation diagram...
Страница 12: ...12 10 2016 TNX65 42 Installation and layout diagrams...
Страница 24: ...24 22 10 2021 TNX65 42 Preparing to transport a machine with milling unit Transport retainer tool changer...
Страница 42: ...42 22 10 2021 TNX65 42 Installing the machine Transport retainer for workpiece handling...
Страница 43: ...43 22 10 2021 TNX65 42 Installing the machine Transport retainer for tool changer if necessary...
Страница 44: ...44 22 10 2021 TNX65 42 Installing the machine...
Страница 52: ...52 10 2016 TNX65 42 Fuels...
Страница 54: ...54 10 2016 TNX65 42 Pneumatic connection...
Страница 56: ...56 05 2017 TNX65 42 Electrical connection...
Страница 62: ...62 10 2016 TNX65 42 Alignment component installation and commissioning...
Страница 63: ......