37
22.10.2021
TNX65/42
Installing the machine
Lifting the machine with hydraulic jacks
There are two U-sections on both the right and left-hand sides of the machine
for positioning the hydraulic jacks.
• Uniformly raise the machine with the aid of the jacks.
The wooden planks are screwed onto the four feet on the machine.
• Unscrew the wooden planks (if they have not been removed already
• If the rear wheel has been removed for transport, it must now be
screwed back into place.
Positioning the transport rollers
Always place the rigid transport rollers under the machine first, and then place
the steerable roller at the appropriate point under the machine.
The load must always be lowered onto the rigid transport rollers first.
The object to be transported must rest on the middle of the
rotating plate on the steered transport roller so that the steering
column can move freely.
Ensure that the four wheels on the control cabinet have been
screwed in completely.
• Carefully lower the load onto the rigid transport rollers and secure it so that
it cannot roll away inadvertently.
• Carefully lower the load onto the steerable transport roller.
• Move the machine to its installation site and secure the transport rollers so
they cannot roll away inadvertently.
• First position the hydraulic jacks on the side of the machine with the
steerable transport roller and lift it uniformly until the roller can be pulled out.
• Lower the machine onto the feet slowly and uniformly.
• Lift the other side of the machine until both transport rollers can be pulled
out. Lower the machine slowly and uniformly onto the positioning
elements.
Rough alignment of the machine
• Place a spirit level lengthwise on the clamping cylinder and crosswise on the
hood.
• The distance from the floor must equal 70 mm at all four installation points.
• Adjust the four outer feet and align the machine with the aid of the spirit
level.
• Secure the adjusting screws of the feet with the locknuts.
Содержание TNX42
Страница 6: ...6 22 10 2021 TNX65 42 Table of contents...
Страница 8: ...8 10 2016 TNX65 42 Safety...
Страница 11: ...11 10 2016 TNX65 42 Installation and layout diagrams Installation diagram...
Страница 12: ...12 10 2016 TNX65 42 Installation and layout diagrams...
Страница 24: ...24 22 10 2021 TNX65 42 Preparing to transport a machine with milling unit Transport retainer tool changer...
Страница 42: ...42 22 10 2021 TNX65 42 Installing the machine Transport retainer for workpiece handling...
Страница 43: ...43 22 10 2021 TNX65 42 Installing the machine Transport retainer for tool changer if necessary...
Страница 44: ...44 22 10 2021 TNX65 42 Installing the machine...
Страница 52: ...52 10 2016 TNX65 42 Fuels...
Страница 54: ...54 10 2016 TNX65 42 Pneumatic connection...
Страница 56: ...56 05 2017 TNX65 42 Electrical connection...
Страница 62: ...62 10 2016 TNX65 42 Alignment component installation and commissioning...
Страница 63: ......