TRAK Machine Tools
Site Preparation Guide
TRAK DPMRX2
F16467-44 Rev 062518
Page 3 of 4
Lifting and/or Moving the Machine
Method 1 (see Figure 1):
1.
Insert a steel bar 1.0" dia x 36" long through the rear side
holes of the bed (under column).
2.
Use a steel cable (with protective covering) min. 3/4" dia. or
a 3 ton sling.
3.
Use cardboard pieces or other suitable protective sheets on
both sides of the machine to prevent scratching.
4.
Remove the 4 nuts and screws holding the machine to the
wood skid.
5.
Lift the machine (the front side of the machine should be
lower than the back side).
6.
Insert the 4 screws for leveling pads in their place in the bed.
7.
Place the machine in its location (see floor plan and bed
footprint drawing) carefully positioning each leveling pad
under each leveling screw.
8.
Remove the lifting cable or sling, the steel bar and all
protective cardboard.
CAUTION!
The DPMRX2 machines weigh approximately 3300 lbs.
Proper equipment of sufficient capacity must be used
when lifting and/or moving the machine.
Figure 1 Lifting the Machine Method 1