Lifting and/or Moving the Machine 

 

 

Method 1 (see Figure 1): 

 

1.

 

Insert a steel bar 1.0" dia x 36" long through the rear side 
holes of the bed (under column). 

2.

 

Use a steel cable (with protective covering) min. 3/4" dia. or 
a 3 ton sling.   

3.

 

Use cardboard pieces or other suitable protective sheets on 
both sides of the machine to prevent scratching.   

4.

 

Remove the 4 nuts and screws holding the machine to the 

wood skid. 

5.

 

Lift the machine (the front side of the machine should be 

lower than the back side). 

6.

 

Insert the 4 screws for leveling pads in their place in the bed.   

7.

 

Place the machine in its location (see floor plan and bed 

footprint drawing) carefully positioning each leveling pad 
under each leveling screw. 

8.

 

Remove the lifting cable or sling, the steel bar and all 
protective cardboard. 

CAUTION! 

The DPMRX2 machines weigh approximately 3300 lbs. 
Proper equipment of sufficient capacity must be used 

when lifting and/or moving the machine. 

Figure 1 Lifting the Machine Method 1

 

 

Содержание DPMRX2

Страница 1: ...low clearance at the rear of the mill to open and work on the electrical box A solid and level foundation to maintain approximately 3300 lbs plus the weight of the workpiece maximum total 4620 lbs is required Six leveling screws are provided Electrical Machine is only available in the 208 VAC configuration 200 to 240V is acceptable A separate 208V 27 amps 60 Hz 3 phase circuit is required For shop...

Страница 2: ... machine With Mechanical handwheel 69 K1 Width of machine Electronic handwheel 71 625 L1 Length of machine with electrical cabinet closed With electronic handwheel 73 3125 M Maximum height of machine from bottom of leveling pads to top of spindle motor with the head all the way up 91 75 Note Removing the z axis motor z axis motor cover resistor housing resistor housing lid and unscrewing the top r...

Страница 3: ...emove the 4 nuts and screws holding the machine to the wood skid 5 Lift the machine the front side of the machine should be lower than the back side 6 Insert the 4 screws for leveling pads in their place in the bed 7 Place the machine in its location see floor plan and bed footprint drawing carefully positioning each leveling pad under each leveling screw 8 Remove the lifting cable or sling the st...

Страница 4: ...d over a suitable lift truck 3 Lift the machine up somewhat tilted towards the front 4 6 from the ground and move it to its floor plan position WARNING The lift truck must have sufficient lifting capacity 3 tons and be equipped with suitably long forks 4 Insert the 4 screws for the leveling pads in their place in the bed 5 Place the machine in its location see floor plan bed footprint carefully po...

Отзывы: