INSTALLATION PROCEDURES:
1. For rough-in dimensions, see Installation Diagram on page 9.
2. The bathtub must be set on a solid flat surface capable of supporting the tub using all six (6) adjustable
feet. It is required that all six (6) feet come in contact with the floor.
3. The plumbing connections (faucet, hoses, and waste/overflow) should be made prior to setting the tub in
place.
4. The filler panel is used only for 60” installations.
5. The door drain assembly is attached at one end at the factory. The drain body is to be installed between
the drain shoe and the drain tee.
NOTE:
The drain body and hose must be installed horizontal. See door drain illustration below.
ELECTRICAL INSTRUCTIONS: HYDRO & AIR MASSAGE WIRING USA
1. The Whirlpool and Air Massage Systems require two (2) dedicated 15-amp 120-volt GFCI circuits.
2. Two receptacles, each with a 15-amp configuration, must be provided by the electrician.
NOTE:
Provide a power supply outlet (receptacle) appropriately rated for each load. For voltage and current