4200FA Installation and Operation Manual
31
6.3.2
Power Cable Routing and Conduit Placement 50 kVA
The following illustrates the proper cable routing that should be followed during the power connection
process for the 50kVA.
Note: Cabinet show with batteries, cabling is the same for units with internal batteries, internal
transformers, and neither internal batteries nor transformers.
Figure 6-7 50kVA Cable Routing and Terminal Location
Содержание 4200FA Series
Страница 2: ...4200FA Installation and Operation Manual ...
Страница 12: ...vi 4200FA Installation and Operation Manual ...
Страница 16: ...4 4200FA Installation and Operation Manual NOTE This Label for Battery Units Only ...
Страница 110: ...98 4200FA Installation and Operation Manual 36 3 in 922 mm ...
Страница 115: ...4200FA Installation and Operation Manual 103 APPENDIX A Seismic Anchorages ...
Страница 116: ...104 4200FA Installation and Operation Manual ...
Страница 117: ...4200FA Installation and Operation Manual 105 ...
Страница 118: ...106 4200FA Installation and Operation Manual ...
Страница 136: ...124 4200FA Installation and Operation Manual ...
Страница 137: ......