background image

Station Decoder Installation

The station decoder module is available in 1-station, 2-station, or 4-station configuration.
The stand-alone GDC model can handle up to 100 stations per output board. These stations can be connected to the output 

board terminals in any configuration (25 stations connected to each of the four terminal pairs or 100 stations connected to one 

terminal pair, etc.). The decoder modules can be connected in parallel anywhere on the two-wire communication line connected 

to the station terminals. Each station can activate up to two solenoids.

When a Tri-Comm Cellular modem is installed in the 2nd output board position, the maximum number of stations on the 

1st output board is increased up to 200 stations.
It is recommended that the decoder modules are installed in an approved valve box to provide easy access to the wiring.  

Use 3M DBR/Y to waterproof all connectors. 
Recommended Controller-to-Decoder cable: 14 AWG (2.5mm

2

), solid copper, jacketed 2-conductor, direct burial.  

The preferred wire make and model is the Paige Irrigation Wire, Spec P7350D.
Recommended Decoder-to-Solenoid cable: 14 AWG (2.5mm

2

), solid copper, 2-conductor, direct burial. The preferred wire 

make and model is the Paige Irrigation Wire, Spec P7351D.

Burial Depth

Toro recommends that the Controller-to-Decoder and Decoder-to-Solenoid cables should have a minimum cover of 6" 

(150mm). The irrigation plan may specify additional depth to be consistent with the depth of mainline or lateral pipe work and/

or soil conditioning procedures such as aeration. Installation procedures must comply with all applicable local and national 

electrical codes.

  • Use only wire approved for direct burial if installing the wires underground without conduit. 

  • All field wiring splices must be accessible to facilitate troubleshooting and/or service.

Step 1 –  Route communication cable from the controller to the station decoder module installation location.
 

The maximum wire length between the controller and the decoder module is 15,000' (4500m).

Step 2 –  Secure the communication wires to terminal 1 of the GDC output board. White wire onto the 1st terminal and black 

wire onto the second terminal. See Figure 4

Step 3 –  Install the decoder module in a valve box. Record the decoder module’s address number found on the side label. 

This address number identifies the station(s) that the decoder module control. 

Step 4 –  Secure the communication wires to the decoder module’s black and white wires. Connect the black communication 

wire to the black decoder module wire. Connect the remaining communication wire (red or white) to the white 

decoder module wire. Use 3M DBR/Y to properly water-proof all wire connections.

Step 5 –  Route output wires from the decoder module to the solenoid. 
 

The maximum wire length between the decoder module and the solenoid is 410' (125m).

Step 6 –  Connect the solenoid wires to the decoder module’s station wires. The station wires are color coded for easy 

identification. Connect the solid colored (red, green, orange or blue) station wire to the red/white solenoid wire. 

Connect the similar color station wire with black stripe to the black solenoid wire. Use 3M DBR/Y to properly water-

proof all wire connections.

Step 7 –  Connect an additional solenoid to the station wire as necessary. 
 

Each station has a maximum load of two solenoids.

Step 8 –  Repeat Steps 3–8 for additional decoder modules.  

 

Содержание GDC 200

Страница 1: ...location that shades the controller during the hottest hours of the day and provides as much protection from direct sunlight rain wind and snow as possible DO NOT mount the controller where it is expo...

Страница 2: ...er wire near the top of the ground rod Avoiding wire bends of less than 8 20 3cm radius and more than 90 route the wire through conduit and into the cabinet Secure the wire to the copper ground lug Ma...

Страница 3: ...e power cables and secure them to the terminal block Reference Table 1 for the appropriate type of power connection Step 4 Reinstall the power supply cover Step 5 Apply power to the controller WARNING...

Страница 4: ...ll applicable local and national electrical codes Use only wire approved for direct burial if installing the wires underground without conduit All field wiring splices must be accessible to facilitate...

Страница 5: ...ation Wire Connect to the Red White solenoid wire Green with Black Stripe Station Wire Connect to the Black solenoid wire Station 3 Solid Orange Station Wire Connect to the Red White solenoid wire Ora...

Страница 6: ...m the decoder and controller to decoder cable Use 3M DBR Y to properly water proof all wire connections See Figure 5 Step 4 Connect the lightning arrester s ground wire to the ground rod or plate s wi...

Страница 7: ...ontrol a master valve or a pump relay if the system requires it Step 1 Place the controller s power switch to OFF Step 2 Connect the Positive Hot wire of the power source that controls the master valv...

Страница 8: ...the ribbon cable back to the timing mechanism socket Step 8 Place the controller s switch to ON Electromagnetic Compatibility Domestic This equipment has been tested and found to comply with the limit...