13
Please retain instructions for future reference
Step 6:
PENT GABLE TOP INSTALLATION
• Fix Pent Gable Tops to the existing built structure.
• The bottom of the gable top will slot into the top of
the cladding on the panel below. Please ensure the
gable top is positioned centrally
above the side panels before
screwing in place.
• Secure through top of side
panels using 2x 50mm
(S50)
screws per gable top.
(Detail N)
Step 7:
PENT HIGH SIDE TOP INSTALLATION
• Fix Pent High Side Tops to existing built structure.
The bottom of the High Side Top will slot into the
top of the cladding on the panel below. Please
ensure the High Side Top is positioned centrally
above the side panels before screwing in place.
• For all models, secure through top of side panels using
2x 50mm
(S50)
screws per High Side Top.
(Detail O)
• For all models, secure through side of High Side Top
into the Pent Gable Top using 1x 50mm
(S50)
screw
per gable top.
(Detail P)
• For models with High Side Tops butting together,
secure through side using 1x 50mm
(S50)
screw
per join.
(Detail Q)
S50
S50
N
Q
O
P
S50
S50
S50
S50