17
Integral Air-Cooled Condenser Check
Make sure the chiller is installed as described in the
mechanical installation section of this manual. Check
to make sure the chiller condenser is clear of
obstructions and has at least 36 inches of open air
on the air inlet and outlets for proper airflow.
Water-Cooled Condenser Check
Check the condenser water lines to make sure all
connections are secure. Make sure sufficient
condenser water flow and pressure are available and
all shut-off valves are open.
Remote Air-Cooled Condenser Check
Check the refrigerant lines to make sure all
connections are secure and that a proper evacuation
of the chiller, the field piping, and the remote
condenser has occurred. Verify the refrigeration
piping is installed as described in the installation
section of this manual. Check the remote condenser
main power and control wiring to ensure all
connections are secure.
Step 4 – Check Refrigerant Valves
During shipment or installation it is possible valves
where closed. Verify that all refrigerant valves are
open.
CAUTION: Do not operate the unit with the
compressor, oil line, or liquid line service
valves “CLOSED”. Failure to have these “OPEN”
may cause serious compressor damage.
Step 5 – Verify Freezestat Setting
Make sure the Freezestat setting is appropriate for
the operating conditions of the chiller. It should be
set at 10°F below the minimum chilled water
temperature setting that the chiller will be operating.
Reference Table 14 to be sure the coolant solution
has sufficient freeze protection (glycol) to handle at
least 5°F below the Freezestat setting. All chillers
ship from the factory with the Freezestat set at 38°F
to protect against a possible freeze-up if no glycol is
in coolant. Once the proper glycol solution is
present, adjust the Freezestat to the appropriate
setting.
CAUTION: The manufacturer’s warranty does not
cover the evaporator from freezing. It is vital that
the Freezestat is set properly.
Step 6 – Turn On Control Power
Some chillers may have a control power switch. If
present, turn the control power switch on. If not
present, turning the main power on should turn the
control power on. When the control power is on, the
panel displays are illuminated. Due to extreme
ambient temperatures that may occur during
shipment, the High Refrigerant Pressure switch may
have tripped. If this is the case, disconnect the main
power and reset the High Refrigerant Pressure by
depressing the manual reset button located on the
switch. Reconnect the main power, turn the control
power on, and clear the alarm condition by pressing
the Alarm Reset button.
Step 7 – Establish Coolant Flow
Standard units have an internal pump. To energize
the pump press the Start button. If the unit does not
have an internal pump, energize the external pump
to establish flow through the chiller.
Note: The compressor will not start as long as the flow switch
is open. A positive flow through the evaporator is required
before the compressor can operate.
Set water flow using a discharge throttling valve or
flow control valve (by others). The valve should be
the same size as the To Process connection of the
chiller. Standard chillers require approximately 2.4
gpm/ton of nominal capacity. A significant increase
in flow beyond this in a standard chiller may result in
excessive pressure loss and negatively impact chiller
efficiency and in extreme cases may cause premature
wear or damage of internal components.
Step 8 – Intial Unit Operation
Enter the desired leaving fluid temperature on the
control panel. Unless otherwise specified, the chiller
is factory set to deliver coolant at 50°F. Adjust to the
desired operating temperature. The chiller should
now be controlling to the selected temperature.
Please note that if there is insufficient load the
compressor may cycle on and off causing swings in
temperature.
WARNING: Never deactivate the High
Refrigerant Pressure or the Low Compressor
Pressure switch. Failure to heed this warning can
cause serious compressor damage, severe
personal injury, or death.
Содержание Accuchiller EQ Series
Страница 1: ...Installation Operation Manual EQ Series Portable and Remote Condenser Chillers ...
Страница 2: ...Page Intentionally Blank ...
Страница 4: ...Page Intentionally Blank ...
Страница 27: ...Notes ...