Powerwall Stack Kit Installation Manual
Step 4. Join the Powerwall Units
1. Orient the second Powerwall about 2 cm (1 in) in front of the first, with its back cable entry
port facing the hole you drilled in the front of the first Powerwall.
2. (Concealed wiring installations only) Do the following to bridge the gap between the
Powerwall wiring compartments:
•
Locate the bridge piece, conduit nipple, two O-rings, and two insulation bushings.
Figure 12: Powerwall Bridge Assembly (Exploded View)
•
Assemble the conduit nipple, bridge piece and O-rings. Center the bridge and O-rings
on the nipple.
NOTE: Orient the O-rings so that the sides with greater surface area (marked “Box Side”)
point to the outside, toward the Powerwall chassis.
Figure 13: Assembling the Conduit Nipple, Bridge and O-rings