Oxygen Analyzer
Part II: Analysis Unit
Part II: 3-1
Teledyne Analytical Instruments
Installation
Installation of the Model 3010T Analyzer includes:
1. Unpacking, mounting, and interconnecting the Control Unit and
the Analysis Unit
2. Making gas connections to the system
3. Making electrical connections to the system
4. Testing the system.
3.1
Unpacking the Analysis Unit
The analyzer is shipped with all materials needed to install and prepare the
system for operation. Carefully unpack the Analysis Unit and inspect it for
damage. Immediately report any damage to the shipping agent.
3.2
Mounting the Analysis Unit
The Model 3010T Analysis Unit is for use in Class 1, Division 1,
Groups C and D, hazardous environments (group B available).
The standard model is designed for bulkhead mounting. Overall dimen-
sions of the Analysis Unit will vary slightly (less than an inch) due to varia-
tions in dimensions of the main explosion-proof enlclosure. The maximum
footprint will be 19
″
×
12
″
, and maximum height 9.4
″
.
Outline Drawing
D-65478, at the back of this manual, gives the correct mounting dimen-
sions for your unit.
Note: The housing, including the cover, protrudes 8.6 to 9.4
inches
from the base on which it is mounted. Enough clearance is
required in front of the cover to allow the cover to be removed
and to withdraw the Micro-Fuel Cell for replacement. Cell
replacement, with an exploded view of the cell block, is de-
scribed in chapter 5 Maintenance.
Содержание 3010TB
Страница 8: ...viii Model 3010TB Teledyne Analytical Instruments...
Страница 12: ...iv Part I Model 3010TB Oxygen Analyzer Teledyne Analytical Instruments...
Страница 16: ...2 4 Part I 2 Operational Theory Model 3010TB Teledyne Analytical Instruments...
Страница 58: ...iv Part II Model 3010TB Oxygen Analyzer Teledyne Analytical Instruments...
Страница 62: ...1 4 Part II 1 Introduction Model 3010T Teledyne Analytical Instruments...
Страница 98: ...A 10 Appendix Model 3010TB Teledyne Analytical Instruments...