Section 3: Performance Verification
Model 2231A-30-3 Triple-Channel DC Power Supply Performance Verification
3-10
077102700/ July 2014
Performance Verification Procedures
The following conditions must be met before performing these procedures:
1. The device under test (DUT) and all test equipment must have been operating continuously for 20
minutes in an environment that meets the operating range specifications for temperature and
humidity.
Test setup changes affecting the remote sense require an additional 20-minute warm-up period.
2. The procedures are intended to be used in sequence. If it is necessary to partially test the DUT
using an individual test, a 20-minute warm-up period is required for the individual test.
3. You must connect the DUT and the test equipment to the same AC power circuit. Connect the
DUT and test instruments into a common power strip if you are unsure of the AC power circuit
distribution. Connecting the DUT and test instruments into separate AC power circuits can result
in offset voltages between the equipment, which can invalidate this performance verification
procedure.
4. The AC power source for the DUT must match the voltage selector switch setting located on the
bottom of the DUT.
DUT voltage selector
AC source voltage
110
115V
220
230V
Equipment Required
These procedures use external equipment to directly check warranted characteristics. The following