background image

©Copyright Task Force Tips LLC 2014-2018

10

LIZ-060 October 26, 2020 Rev03

4.0 INSTALLATION

4.1 STRUCTURAL REQUIREMENTS

4.2 CONNECTION TO WATER SUPPLY

4.2.1 INSTALLATION ON HUM OR IVUM (SIDE A OPTION H)

1. Install the supplied O-ring onto the barb that protrudes from the bottom flange

of the Booster. Apply silicone grease over the O-ring.

2. Align the Booster with the HUM or IVUM as shown.

3. For the IVUM only, the IVUM Flange Adapter must be oriented such that the

non-threaded counter-bored holes are aligned with screw locations 3 and 5,

and  the  threaded  holes  are  aligned  with  the  other  six  screw  locations.

Orientation  of  the  Booster  to  the  IVUM  is  flexible;  however  it  is  critical  to

choose an orientation such that the LDH Inlet Port C3 on the Booster will not

interfere with the crank handle on the IVUM.

4. Apply Loctite 242 (blue) thread-locking adhesive to (8) supplied ½-13 x 1.5”

screws, then hand tighten into the locations shown until the screw heads are

bottomed out. Screw numbers 3 and 5 are inserted up thru the HUM or IVUM,

then into the Booster. The other six screws are inserted through the Side A

Inlet flange of the Booster.

5. Tighten the (8) screws to 40 to 45 ft-lb (54-61 N-m) torque in the alternating

sequence shown on Figure 4.2.1. Tighten at graduated intervals of 30%, then

60%, and finally 100% of the specified torque.

6. To install the monitor, 

(see section 4.3)

.

4.2.2 BOOSTER OSC INSTALLATION ON HUM OR IVUM (SIDE A 

OPTION H)

1. Depress the red latch and remove the safety Guard from Oscillating Booster.

2. Use 5/16” hex key to remove four 3/8”-16 x 1” long socket head cap screws

from the cover plate surrounding the oscillating gearbox. Remove gearbox from Oscillating Booster and set it aside.

3. Loosen the belts by using an adjustable wrench to tighten the belt tensioner. Remove the top belt from the pulleys first, then

remove the bottom belt. Set parts aside.

4. Use 5/16” hex key to remove four 3/8”-16 x 1.5” long socket head cap screws from the pulley housing. Lift pulley housing away

from Booster body. It may be necessary to pry gently to overcome the adhesion of residual Loctite in the screw holes.

5. Follow steps 1 through 5 in 

Section 4.2.1

.

6. Install pulley housing using the four 3/8”-16 x 1.5” long screws that were originally installed. Apply Loctite 242 blue to screws, then

tighten snug against pulley housing. Maximum torque allowed is 200 in-lb (17 ft-lb, 23 N-m).

7. The two belts are identical. Install one belt over silver-colored input shaft and lower-right pulley. Install other belt between upper

left pulley and lower-right pulley. Back the belt tensioner out until it bottoms out. Verify that belts are seated properly and are taut

between pulleys.

8. Install gearbox over pulleys by pivoting gearbox until the gearbox shaft slides into the socket of the top pulley. Then, pivot the

cover plate until it seats flush against the pulley housing.

9. Apply blue Loctite to four 3/8-16 x 1” long screws and install snug against cover plate. Maximum torque allowed is 200 in-lb (17 ft-

lb, 23 N-m).

10. To install the monitor, 

(see section 4.3)

.

CAUTION

Mismatched or damaged waterway connections may cause equipment to leak or uncouple under 

pressure. Failure could result in injury. Equipment must be mated to matched connections. 

CAUTION

Dissimilar metals coupled together can cause galvanic corrosion that can result in the inability to 

uncouple the connection, or complete loss of engagement over time. Failure could cause injury. Per 

NFPA 1962, if dissimilar metals are left coupled together, an anti-corrosive lubricant should be 

applied to the connection and the coupling should be disconnected and inspected at least 

quarterly. 

WARNING

Reaction forces generated by master stream flows are capable of causing injury and property

damage if not properly supported. Monitors should be securely installed by qualified individuals.

• Mounting objects must be capable of withstanding maximum nozzle reaction force listed in 

SPECIFICATIONS.

• The monitor must be securely mounted to rigid support members.

• Do not use flanges or pipe made from plastic for monitor mounting.

• Torque all fasteners to specified values. 

1

8

4

7

2

6

5

3

3

5

BOOSTER

1/2"-13 X 1 1/2 LONG

SOCKET HEAD CAP SCREW

VT50-13SH1.5  (8 ) PLACES

O-RING-243
VO-243

INDUSTRIAL

VALVE UNDER MONITOR

WITH SIDE B OPTION 0

HYDRANT UNDER MONITOR

WITH SIDE B OPTION 0

IVUM
FLANGE

ADAPTER

Figure 4.2.1

Содержание ZCF1T3

Страница 1: ...s and maintenance personnel with the operation servicing and safety procedures associated with this product This manual should be kept available to all operating and maintenance personnel Model ZCF1T3 integrated with TFT Hydrant Under Monitor and TFT Monsoon Monitor Model ZCH1T1 OSC for attachment to Hydrants Valves and Monitors with 4 ANSI 150 connections Model ZCH1TQ integrated with TFT Industri...

Страница 2: ... The purpose of the proof test is to be con dent the valve design may be safely operated at the rated operating pressure SAMPLE CONFIGURATIONS Model ZBAD31X00 with 4 ANSI 150 on side B 6 Storz on port C1 and blind plug on port C2 Model ZBAD38J8J with 4 ANSI 150 on side B and 2 5 gated wyes on both ports C1 and C2 Model ZBAD11T1T with integrated TFT Typhoon on side B and 5 Storz on both ports C1 an...

Страница 3: ... ANSI 150 FLANGE INLET ADAPTER SIDE A OPTION G 4 3 MONITOR COMPATIBILITY AND INSTALLATION 4 3 1 MONITOR INSTALLATION USING CODE RPM DIRECT CONNECTION SIDE B OPTIONS 1 AND 2 4 3 2 MONITOR INSTALLATION USING 4 ANSI 150 FLANGE SIDE B OPTIONS 3 AND 4 4 3 3 MONITOR ELBOW INSTALL USING QUICK CONNECT COUPLING SIDE B OPTIONS Q AND T 4 3 4 MONITOR INSTALLATION ON BOOSTER OSC 5 0 USING THE BOOSTER BOOSTER O...

Страница 4: ...ply hose may reduce water flow and cause injury or death to persons dependent on water flow Avoid tight bends to minimize risk of hose line kinks WARNING Injury or damage can occur from an inadequately supported monitor The mounting must be capable of supporting the nozzle reaction force which can be as high as 1500 lbs WARNING The stream exiting a nozzle is very powerful and capable of causing in...

Страница 5: ...d An alternate pulley set stored within the safety guard allows the oscillating speed to be doubled by exchanging the pulleys using common hand tools The Booster OSC is compatible with TFT Monsoon Typhoon and Hurricane monitors that are specified with inlet option W swivel base for Booster OSC 3 1 SPECIFICATIONS 0 Table 3 1 3 2 CORROSION RESISTANCE All Booster bodies are hard anodized aluminum whi...

Страница 6: ...long with the corresponding weights and dimensions The model number and unique serial number of each Booster are located on the label above the external automatic drain as shown in Figure 3 4 Go to tft com serial number for additional information about this product Table 3 5 1 Character Position 1 2 3 4 5 6 Component ZC same prefix for all models SIDE A INLET OPTION 3 65 I D LDH INLET PORT C3 3 65...

Страница 7: ...pter installed is designed for direct connection to the Task Force Tips Industrial Valve Under Monitor IVUM and Hydrant Under Monitor HUM Either of these products provide the valve needed to shut off the supply from the Side A Inlet in order to use an alternate supply of water or foam solution from LDH Inlet Port C3 The Side A Inlet is also available with a 4 or 3 ANSI 150 flange adapter to allow ...

Страница 8: ...1T ZCC3 1T 3 2 1 4 6 0 Storz 1X ZCC3 1X 8 7 4 0 3 5 NH female thread 4N ZCC3 4N 3 1 1 4 4 0 NH female thread 4P ZCC3 4P 2 2 1 0 4 5 NH female thread 4R ZCC3 4R 3 6 1 6 5 0 NH female thread 4T ZCC3 4T 3 1 1 4 6 0 NH female thread 4X ZCC3 4X 4 0 1 8 Figure 3 5 4A Storz coupling Female threaded coupling OPTION 1P PART ZCC3 1P 4 0 Storz OPTION 1T PART ZCC3 1T 5 0 Storz OPTION 1X PART ZCC3 1X 6 0 Storz...

Страница 9: ...erlap with the main valve body are excluded from these dimensions SIDE B OPTIONS character position 6 CHARACTER PART NUMBER WEIGHT lb WEIGHT kg CODE RPM DIRECT CONNECTION STRAIGHT 1 A1026 1 8 0 8 CODE RPM DIRECT CONNECTION ANGLED 22 5 2 A1040 2 8 1 3 4 ANSI 150 DN 100 PN16 FLANGE STRAIGHT 3 A1039 1 6 5 3 0 4 ANSI 150 DN 100 PN16 FLANGE ANGLED 22 5 4 A1039 2 7 5 3 4 QUICK CONNECT 4 5 NHM for Monsoo...

Страница 10: ... of residual Loctite in the screw holes 5 Follow steps 1 through 5 in Section 4 2 1 6 Install pulley housing using the four 3 8 16 x 1 5 long screws that were originally installed Apply Loctite 242 blue to screws then tighten snug against pulley housing Maximum torque allowed is 200 in lb 17 ft lb 23 N m 7 The two belts are identical Install one belt over silver colored input shaft and lower right...

Страница 11: ...3 4 2 4 INSTALLATION USING 3 ANSI 150 FLANGE INLET ADAPTER SIDE A OPTION G When Side A option G is specified the 3 ANSI 150 Flange Inlet Adapter is pre installed on side A of the Booster Four 5 8 11 x 3 bolts and thick washers are supplied One of the bolts and an O ring seal are pre installed between the Inlet Adapter and Booster body To install the Booster on a 3 ANSI 150 flange refer to Figure 4...

Страница 12: ...n injury Do not install shutoff valves downstream of Booster Do not exceed the lowest maximum operating pressure rating of any devices assembled together Do not exceed the lowest maximum flow of any of the devices assembled together Do not install monitor extension pipes between Booster and monitor such as Task Force Tips Extend A Gun Akron 3406 or Elkhart Extender Do not exceed 20 508 mm monitor ...

Страница 13: ...y does not interfere with RC monitor Power Com Cable if applicable Reposition Clamp if needed 5 Tighten each screw gradually until both are finger tight with approximately equal spacing between opposite ends of Clamp 1 Carefully tighten each screw one additional turn using a 5 32 hex wrench by alternating to the opposite screw in half turn increments until tight Over tightening screws will damage ...

Страница 14: ... specified with inlet option W swivel base for Booster OSC only 1 Verify O ring size 243 is installed on monitor inlet barb and is free of debris Apply silicone grease over O ring 2 Depress the red latch and remove the safety guard from Oscillating Booster 3 Use 5 16 hex key to remove eight 3 8 16 x 1 25 screws from outlet of Oscillating Booster Set screws aside Apply blue Loctite to the eight scr...

Страница 15: ...source to boost the pressure available to the monitor Port C3 also allows an inline eductor or other foam injection system to be attached to supply foam solution to the monitor See Section 6 0 on page 21 to estimate the performance of each inlet used independently Port C3 can serve as the primary inlet to the monitor during periods when water mains are not operational by providing fire protection ...

Страница 16: ...For water supplies from other sources follow the instructions below 1 Close valve installed upstream of the Booster Side A Inlet 2 Connect a hose from the water supply to LDH Inlet Port C3 of the Booster Pumps and or foam injection devices should be connected in this hose line 3 After all connections have been made introduce the water supply When water reaches the Booster the swing check valve cla...

Страница 17: ... with vehicle access routs maintained using hose bridges when needed The Booster and monitor can be relocated again and again to coordinate with re construction progress of fire main replacement programs outages and for protection of temporary fire hazards 5 2 3 1 TEMPORARY FIRE PROTECTION USING HOSE Figure 5 2 3 1 5 2 3 2 DIRECT CONNECTION WITH BROKEN WATER MAIN Figure 5 2 3 2 Hydrant In Service ...

Страница 18: ...v03 5 2 3 3 DIRECT CONNECT WITH BROKEN HYDRANT Figure 5 2 3 3 5 2 3 4 CONNECTION WHEN THERE IS NO WATER MAIN Figure 5 2 3 4 MONITOR BOOSTER BLIND FLANGE HYDRANT HOSE FLOW PORT C3 OUT OF SERVICE PORT C3 MONITOR BOOSTER BLIND FLANGE CONCRETE HOSE FLOW PORT C3 FORKLIFT SLOTS ...

Страница 19: ... use a wrench to manually rotate the external OSC drive hex shaft and then pivot the monitor by hand B When flowing Continue to gently push the monitor against the toggle point As the oscillating mechanism continues to rotate it will eventually allow the angle adjustment disc to reach the desired setting 3 When desired setting is reached release pull pin and adjust the monitor slightly until pull ...

Страница 20: ...ve 20 x 75 long screw from center of one pulley and set the parts aside temporarily Repeat for other pulley 3 Loosen thumb nut Section 8 2 number 9 on bottom of safety guard section 8 2 number 2 Remove 8 cycle min pulleys from safety guard and slide original 4 cycle min pulleys into safety guard instead Install thumb nut snug against bottom pulley 4 Slide screws into pulleys and apply blue Loctite...

Страница 21: ...de B outlet of the Booster only and does not include pressure losses of any upstream or downstream equipment such as hoses monitors and nozzles Figure 6 0 0 0 5 1 1 5 2 2 5 3 0 2000 4000 6000 8000 0 5 10 15 20 25 30 35 0 500 1000 1500 2000 2500 LOSS BAR FLOW litres min LOSS PSI FLOW GPM Flow from LDH Inlet Port C3 all models ZCH models only Flow from Side A mounted on TFT HUM or IVUM ZCF models on...

Страница 22: ...rge of its obligations under this limited warranty If TFT makes this election claimant shall return the equipment to TFT free and clear of any liens and encumbrances This is a limited warranty The original purchaser of the equipment any person to whom it is transferred and any person who is an intended or unintended beneficiary of the equipment shall not be entitled to recover from TFT any consequ...

Страница 23: ...6 8 1 SERVICE TESTING In accordance with NFPA 1962 equipment must be tested a minimum of annually Units failing any part of this test must be removed from service repaired and retested upon completion of the repair 8 2 REPAIR Factory service is available with repair time seldom exceeding one day in our facility Factory serviced equipment is repaired by experienced technicians wet tested to origina...

Страница 24: ...PLACED BACK IN SERVICE appliances must be inspected to this list 1 There is no obvious damage such as missing broken or loose parts dents cracks corrosion or other defects that could impair operation 2 The waterway is clear of obstructions 3 Valves opens and closes smoothly and fully 4 There is no damage to any thread or other type connection 5 All locks and hold down devices work properly 6 Inter...

Отзывы: