Installation Instructions
Targetti USA - A Targetti Group Company - 750-A W. 17th. St. Costa Mesa, CA 92627 - (714)
513-1991 Email: [email protected] - www.targetti.us -
02.2020
- Page 2 of 4
A.
Installers will dig out trenches to prep the sleeve
i.
Put gravel in the trenches for the J-Box
.
Requirement by UL for
adequate drainage
.
ii.
Safety net covers
below
the J-Box and the conduit
pipe
to warn
diggers
what is
below
.
B.
Position of the J-Box must be an accessible depth between
8.5-11.5"
required
for
maintenance
.
C.
Once the sleeve is installed, wire the
fixture's
power cable through the
J-
Box and connect the power cord to the
J-Box wiring
.
Make sure
the power
is not live before connecting power cord to line
voltage through the J-
Box.
Once power cord is connected,
connect the power cord with the fixture.
Be sure to
secure
the
connection
with water tight connectors
to ensure no
water
leakage inside the
connector.
Incoming conduit
system for line
voltage power
Sleeve for fixture
A
B
C
Gravel for drainage
Fixture's p
ower
c
able
. Connect
with line voltage
power.
Outgoing conduit
system for line
voltage power
Incoming conduit
system. Connect to J-
Box with 3/4" NPT
connector.
Out-going
conduit
system. Connect to J-
Box with 3/4" NPT
connector.
Brass direct
burial J-Box