7.
COMMISSIONING
7.1.
Pre-checks
Commissioning of the products not containing electric heater may only be done by staff specially
trained for the job. If you wish, these products also can be commissioned by TANPERA service free of
charge.
Check if all connections are fitted correctly (see also 6.4).
7.2.
Operation
When commissioning the product, follow these steps:
• Open the hot water tap located farthest in the system.
• Open the valves of all domestic water connections on the tank, except for the cold water inlet.
• Open the cold water inlet valve and start filling the tank and system with water.
• Close the tap when the water flowing from the hot water tap begins to flow airless.
• After ensuring that the tank is completely filled with water, check all connections and piping
for leaks. This control can be made by visual inspection or by monitoring the pressure drop
from the manometer in the installation.
Commissioning of products containing electric heater must be carried out by an authorized
TANPERA service organisation. This process is free of charge and the products that are not
commissioned by an authorised TANPERA service are not covered by the warranty.
Never operate the heating system when the tank is not completely filled with water.
11
We reserve the right to make changes in technical information.
• For TSB and
TDB
, open the inlet/outlet valves of the heating coils and fill them with heating
water. Start the circulation by starting the pump and bleed the system.
Check the pressures and temperatures of the media and make sure that these
are within the limit