safety requirements

Tabi aura - Wall Mounted Frameless Dry Erase 
Board, Non-Seismic Applications
The building’s Engineer of Record must be 
consulted to determine if there are any seismic 
requirements.

Minimum Required Wall Construction

Drywall with metal studs:

•  Must be at least 25 ga. (0.018” thick) 33 ksi steel studs 

(1.5” x 3.5”)

•  Studs on maximum 24” centers
•  Must be at least 5/8” thick Type X gypsum drywall 
•  #6 x 1-1/4” drywall screws on 12” centers 

Verify Wall Construction

•  CAUTION! Adequate wall construction is required 

to support the weight of the board. Minimum wall 
construction must be capable of supporting weight 
amounts listed in Table 1.

Drywall with wood studs:

•  Stud grade SPF, DF-L or Hem-Fir (1.5” x 3.5”)
•  Studs on 24” centers
•  Must be at least 5/8” thick Type X gypsum drywall 
•  #6 x 1-1/4” drywall screws on 12” centers

Read all assembly direction before beginning installation. 
Building construction varies greatly. The Building’s Engineer 

of Record is responsible for the design of building walls which 

the boards are attached to and must verify the adequacy of the 

mounting hardware, even if provided by the manufacturer. 
The building owner or designated agent is responsible for 

verifying that the installation is in compliance with all local codes 

and regulations. 

Lisez l’ensemble des instructions d’assemblage avant de 

démarrer l’installation. 
La construction des bâtiment varie grandement. L’ingénieur 

d’enregistrement du bâtiment est responsable de la conception 

des murs sur lesquels sont attachées les planches et doit vérifier 

que le matériel de montage est adéquat, même si ce dernier est 

fourni par le fabricant. 
Le propiétaire du bâtiment ou l’agent désigné a la responsabilité 

de vérifier que l’installation est comforme a l’ensemble des codes 

et réglementations locaux.

CRUSH HAZARD. Failure to properly 

secure board could result in personal injury.

RISQUE D’ÉCRASEMENT. Ne pas attacher 

la planche de manière sûre pourrait 

entrainer des blessures personnelles. 

CAUTION!

ATTENTION!

SAFETY INSTRUCTIONS

INSTRUCTIONS DE SÉCURITÉ

Содержание Aura

Страница 1: ...installation instructions tabi aura Doc 100121 Rev A Page 1 of 8...

Страница 2: ...es greatly The Building s Engineer of Record is responsible for the design of building walls which the boards are attached to and must verify the adequacy of the mounting hardware even if provided by...

Страница 3: ...ous widths Board size determines the quantity of anchors and screws brackets aura panel s wall anchors 1 1 4 self drilling screws Drill 2 Bit Glass suction cup lifters 2 Pliers Pencil Level 2 or 3 ste...

Страница 4: ...ds as often as possible Mounting heights are recommendations only 34 lbs 50 lbs 66 lbs Weight 47 x 48 47 x 72 47 x 96 Size 2 3 4 of studs Recommended Mounting Heights A 75 9 16 B 46 5 8 Horizontal Ori...

Страница 5: ...Level brackets and mark holes onto wall Refer to recommended mounting heights noted on page 4 step three Remove brackets from wall and install wall anchors in all hole locations that are not over a s...

Страница 6: ...tep five Lower brackets on back of the Aura board onto brackets on wall IMPORTANT Always check to insure both top and bottom panel brackets are resting on the wall brackets NOTE The top and bottom of...

Страница 7: ...Page 7 of 8 Doc 100121 Rev A installation instructions step five continued NOTE Consider using glass suction cups when mounting panel Installation of Aura is now complete...

Страница 8: ...of PolyVision Corporation or their respective owner PolyVision Corporation reserves the right to make changes in product design construction or detail and to discontinue any product or material withou...

Отзывы: