8. Commissioning
8.1
Safety information
»
Commissioning may only be carried out by trained and instructed qualified personnel!
8.2 Preconditions
»
Installation and electrical connection have been correctly performed.
»
Residual material from installation and foreign objects have been removed from the fan and ducts.
»
Inlet and outlet are free.
»
The safety devices have been fitted (protective grille).
»
The earth wire is connected.
»
The cable glands are tight.
»
The nominal current (from the name plate) is not exceeded.
»
The data on the name plate corresponds with the connection data.
»
The supply voltage corresponds with the device voltage.
8.3
Tests when activated
Switch the ventilator on.
WARNING
Danger from protruding parts!
»
Wear safety goggles when checking the direction of rotation.
Check the direction of rotation/conveyance. The direction of rotation always applies looking at the rotor.
WARNING
Danger from electrical voltage!
»
Ensure that all phases are completely free of voltage.
»
Observe the 5 rules of electrical safety (see section 2.5)!
Check:
»
Smooth running (any vibrations and noise)
»
Current consumption (with appropriate measuring instrument)
»
Tightness of all connections