background image

4.   Seat the O-ring or gasket against the saddle and mount the detector di-

rectly to the pipe. Carefully roll the vane opposite the direction of flow 
and insert it through the hole. Seat the saddle firmly against the pipe so 
that the locating boss goes into the hole.

5.   Install  the  U-bolt,  tightening  the  nuts  alternately  to  ensure  a  uniform 

seal. See 

Table 1

 for torque values.

6.   Remove the metal cover with the tamper-proof wrench provided. Manu-

ally actuate the limit to check for binding. If the vane binds, remove the 
detector and correct the cause before proceeding.

CAUTION

Be sure the direction-of-flow arrow points in the right direction or else water 
flow will go unreported. See 

Figure 3

.

fiGUre 1. moUnTinG dimensions:

6.75˝

4.019˝

5.019˝

PLASTIC 

VANE

PIPE 

DIAMETER 

PLUS 6.5˝

PIPE

U-BOLT 

NUT

PIPE 

SADDLE

U-BOLT

W0238-00

fiGUre 2. moUnTinG hoLe LocaTion:

WRONG

RIGHT

REMOVE BURRS FROM EDGE OF HOLE. CLEAN OUT SCALE

AND FOREIGN MATTER FROM INSIDE WALL OF PIPE.

W0106-00

TabLe 1:

Wfd Model

Hole Size (in)

ToRque

20, 25, 35

1

1

/

4

30–35 ft.-lb.

30-2, 40, 50, 60, 80

2

55–60 ft.-lb.

D770-24-00 

I56-1452-005R

PreoPeraTion TesTinG 

1.   Fill the sprinkler system and check for leaks around the waterflow detec-

tor. If it leaks, first check for the proper torque on the U-bolt nuts. If the 
leak persists, drain the system and remove the detector (refer to Mainte-
nance). Check for dirt or foreign objects under the gasket, and make sure 
that the pipe surface is not dented. Reinstall the detector and check again 
for leaks. Do not proceed until all leaks have been stopped.

2.   Connect  an  ohmmeter  or  continuity  tester  across  the  COM  and  B-NO 

switch terminals. The ohmmeter should indicate an open circuit.

3.   Deflect  the  actuator  lever  and  hold  it  until  the  pneumatic  delay  shaft 

releases the switch buttons. The ohmmeter or continuity tester should 
show  a  short  circuit  after  the  delay  has  elapsed.  If  there  is  no  delay, 
check the setting of the delay adjustment dial.

fiGUre 3. assembLY diaGram:

COVER

TERMINAL BLOCK 

(REPLACEMENT P/N A77-01-02)

GROUND 

SCREW 

(GREEN)

CONDUIT 

ENTERANCE

U-BOLT NUT

DIRECTION OF 

FLOW ARROW

PIPE

U-BOLT

DELAY 

MECHANISM 

(REPLACEMENT P/N 

A3008-00)

PIPE SADDLE

PLASTIC VANE

ROLL PADDLE (VANE) 

OPPOSITE OF FLOW 

ARROW WHILE INSERTING

SADDLE 

GASKET

HOLE SIZE

(REFER TO TABLE 1)

W0183-00

WirinG

1.    All  models  have  two  SPDT  switches.  Switch  contacts  COM  and  B-NO 

are closed when water is flowing and open when it is not. Connect the 
switches, as shown in 

Figure 4

, depending on the application.

2.    When connected to a listed sprinkler/fire alarm control panel, the initiat-

ing circuit must be non-silenceable.

3.    A ground screw is provided with all waterflow detectors. When ground-

ing is required, clamp wire with screw in hole located between conduit 
entrance holes. See 

Figure 3

.

4.   If a second conduit entry is required, remove the plug using a hex wrench. 

WARninG

High Voltage. Electrocution Hazard. Do not handle live AC wiring or work on a 
device to which AC power is applied. Doing so may result in injury or death.

When utilizing switches at voltages greater than 74VDC 

 or 49VAC 

 

means  to  provide  all–pole  disconnection  must  be  incorporated  in  the  fixed 
wiring, such as a circuit breaker.

firealarmresources.com

Отзывы: