5.2 Installation of the LPR-2DB Integral Station
TPB000250 (LPR-2DB Integral)
TPB000251 (LPR-2DB Integral)
TPB000530 (LPR-2DB Integral, cell coordinator)
All installation, repair and servicing work must be carried out by qualified
and trained electrical technicians!
5.2.1
Electrical Interface
The bases can be connected via the terminal block.
Polarity reversal or incorrect connection will damage the Integral
Station. If this happens, the LPR-2DB Integral Station must be returned