background image

3

                                                                20220811 - L00009 (1.2)          Swegon reserves the right to alter specifications.

Actionair 

SPAN Installation Guide

Horioztonal Damper Installation 

SPAN (access side above)

Actionair SmokeShield PTC - [AA/F 12368]

Installation Method

1. Bolt Unistrut (1.5mm minimum thickness) supports to 

4 damper cleats and position damper in aperture with 
minimum M10 bolts.

2. 

Fix Unistrut supports to the floor with minimum ø6mm 
fire rated fixings.

3. Shutter underneath with 50mm thick Shutterbatt.

IMPORTANT – to prevent any compound pouring into 
the damper interface shroud and rendering the damper 
inoperable the following MUST be followed: Do NOT 
remove damper interface transit plate. Tape up under-

neath damper interface shroud. Do NOT fill above 

damper casing

4. 

Using thick consistency compound, trowel in the first 

layer of approximately 25mm, all around the damper 
casing, making sure all the gaps are fully sealed, as per 
industry standard.

5. 

When the first layer has set, pour in the next level to 

100mm thickness. IMPORTANT;Compound must not 
be too watery or runny as it risks penetrating into the 

interface shroud. Do NOT fill above damper casing

6. When compound has fully set, remove damper inter-

face transit plate and check the internal is free from any 
debris, remove any debris.

7. Follow the actuator installation procedure detailed in 

this document.





















Comments:

Rev:

Drawn By:

M. Bushell

Approved By:

Kimberley.M

1  of 2 

Reference No:

Gore.S

Date:
Date:

By:

Date:

13/04/2022

03/04/2018

13/04/2022

Date:

B

Checked By:

Sheet

Rev

AAF12368

Description:

If your proposed installation details differ from 

that shown here, please discuss this with the 

authority having jurisdiction, referencing this 

documentation.  

 

Deviation from this drawing requires approval 

of the relevant authority. 

 

Connecting ductwork omitted for clarity. 

Ductwork must be independently supported.  

There must be an appropriate break-away 

joint between the damper and the connecting 

ductwork on both sides of the installation. 

 

A minimum of 200mm between fire dampers 

installed in separate ducts and 75mm between

fire damper and construction elements/edges 

needs to be observed unless otherwise 

specified in the drawing.

Installation Detail



Damper Size Range (mm)

HORIZONTAL APPLICATION

SMOKE  COMPOUND

SEAL - SPAN, ACCESS SIDE

ABOVE

200 x 200 to 1000 x 1000































 For detailed installation, please 

view document ED-AA-4.

A

ECN1932

MJB 05-11-20







Tape up underneath the damper interface shroud

to protect against penetration of mortar into the

 interface shroud.  It is important that no mortar

 enters the shroud.

 

 

 

 

© Swegon Air Management Limited

South Street, Whitstable, Kent CT5 3DU

Tel:  +44 (0)1227 276100

Email: [email protected]

 www.swegon.com/uk

Please refer to the DoP

for latest classifications

for CE/UKCA

compliance and the

Installation, Operation

and Maintenance Guide

 SCAN ME

B

ECN2227

MJB 13/04/22

Содержание Actionair SmokeShield PTC

Страница 1: ...nt supplier Actuators All wiring should be carried out in accor dance with the wiring details provided by the IEE and BS regulations and by a competent person Care must be taken when installing and inspecting dampers as they are likely to close without warning due to loss of electrical power or a temperature rise in the ductwork This is their prime function Do not insert any items fingers or limbs...

Страница 2: ... with fire separating elements to maintain fire compart ments The SmokeShield is an actuated failsafe close damper with low smoke leakage often referred to in the industry as a Fire Smoke damper Under the Fire Damper Product standard BS EN 15650 our Fire Damper products are tested to BS EN 1366 2 and classified under BS EN 13501 3 For smoke control the product you use should be tested to BS EN 121...

Страница 3: ...nto the interface shroud Do NOT fill above damper casing 6 When compound has fully set remove damper inter face transit plate and check the internal is free from any debris remove any debris 7 Follow the actuator installation procedure detailed in this document Comments Rev Drawn By M Bushell Approved By Kimberley M 1 Reference No Gore S Checked By AAF12368 Description If your proposed installatio...

Страница 4: ...d the damper casing making sure all the gaps are fully sealed as per industry standard 8 When the first layer has set pour in the next level to 100mm thickness IMPORTANT Compound must not be too watery or runny as it risks penetrating into the interface shroud do NOT fill above damper casing against penetration of compound into interface shroud 9 When compound has fully set remove the shutterbatt ...

Страница 5: ...n Both screws should be tightened fully to ensure that both sections of the ETR are closed together It is a safety feature if both sections are not closed the unit will not operate For ductless installations the ETR should be fitted onto the damper spigot not casing above the damper interface shroud and in accordance with the fitting instructions If the ETR is not fitted in the exact manner descri...

Страница 6: ...s A comprehensive example of the maintenance pro cedure is given in Annex D of the standard Some automatic systems may allow more frequent testing 48hr or less and this may be required by a national standard Approved Document B Volume 2 Clause 10 12 states adequate means of access must be provided to allow inspection testing and maintenance of both fire damper and its actuating mechanism BS 9999 2...

Страница 7: ...LY OPEN AC DC 230V 50 60 Hz 14 VA 12 4 W 30 C 50 C CONTINUOUS TF 72 C AC 250V 6 3 A N CONTINUITY WITH COMMON ELECTRICAL THERMAL RELEASE ETR MUST BE FITTED TO DUCTING FOR DAMPER OPERATION SPRING BIASED TEST SWITCH WHEN DAMPER CLOSED CONTINUITY WITH COMMON WHEN DAMPER OPEN CONTINUITY WITH COMMON WHEN DAMPER CLOSED CONTINUITY WITH COMMON WHEN DAMPER OPEN Supply Off Damper spring closes Mode 5 3P PTC ...

Страница 8: ...H WIDTHS AND HEIGHTS OF 200 1000MM FOR DUCT WIDTHS AND HEIGHTS OF 151 199MM FOR DUCT WIDTHS 200MM 1000MM WITH HEIGHTS OF 100 199MM Base Dampers Circular Dampers Series 601 For Circular and Flat Oval Dampers spigots are 3mm under duct size Diameters and flat oval diameters in 1mm increments Circular Dampers Series 601 FOR DAMPERS 100 150MM D FOR CIRCULAR AMPERS SERIES 601 DIAMETERS 151 199MM 2 FOR ...

Страница 9: ...red Check wiring in accordance with procedures The ETR cables have been damaged or tampered with Replace with new mode Control Mode operates but limited or no movement of damper blades is observed The mode is not correctly synchronised with the inter face Remove motor from interface Check motor in fully released state Set position of interface and refit motor with label upmost include motor locati...

Страница 10: ...pening will invalidate the installation method Damper installer to advise the lead contractor if problems are foreseen 8 Using the access opening provided check that blades open and close Check position of damper blades 9 Has the damper been checked for internal cleanliness free from damage and that vertical casings in particular are free from debris With the damper in the closed position inspect ...

Страница 11: ...11 20220811 L00009 1 2 Swegon reserves the right to alter specifications Actionair SPAN Installation Guide Notes ...

Отзывы:

Похожие инструкции для Actionair SmokeShield PTC