Inspection and handover check sheet

This certificate applies only to Swegon Fire Dampers. The installer must complete this installation certificate when instal

-

ling fire and smoke dampers. A separate certificate must be completed for each individual fire and smoke damper.

Question

Action

1

Are the dampers the correct type?

Confirm damper is correct type for the application

2

Are the dampers located correctly?

The damper location is to be checked against the installation 

drawings/details

3

Are the dampers correctly identified?

Unique system ID to be clearly indicated on the damper or 

other agreed location.

4

Have supports for both the damper and the adjacent 

ductwork been installed in accordance with the appro-

ved manner?

5

Are the dampers fitted in the correct orientation?

Confirm the damper is installed with any actuators (if applica

-

ble) on the left or right hand side. Not on the top or the bot-

tom (i.e. blade pivot running vertically) unless permitted under 

the respective DoP.

6

Is access through the ductwork, to the damper unob-

structed?

Unobstructed space should be provided for safe access to the 

damper. This must include access through ceiling voids and ad-

jacent services. Damper installer to advise the system designer 

if problems are foreseen.

7

Has the space around the damper and within the 

opening been left clear and not been used for other 

services?

Other services within the installation opening will invalidate 

the installation method. Damper installer to advise the lead 

contractor if problems are foreseen.

8

Using the access opening provided, check that blades 

open and close.

Check position of damper blades.

9

Has the damper been checked for internal cleanliness, 

free from damage and that vertical casings in particular 

are free from debris?

With the damper in the closed position, inspect for damage.

10

Has the damper been released to simulate operation of 

the thermal release? (Damper drop test)

Ensure damper operation is free from interference.

11

Have the damper blades been re-set following drop 

test and the access panel replaced?

After re-setting the damper, check the position shown on the 

blade position indicator is correct.

12

At the time of damper handover, is the fire barrier and 

penetration seal complete?

Damper installer to record on the handover register if  

any following trades are still to complete their activities.

13

Is the damper installation complete and available for 

handover prior to system commissioning?

Obtain the relevant acceptance of the damper installation from 

the CDM coordinator.

14

Is the completed handover register cross-referenced 

back to the identification codes listed in the system 

designers damper schedule?

Damper Unique System I.D: ..........................................................................................................................................................
Name of installation location:......................................................................................................................................................... 
Address:............................................................................................................................................................................................ 

Installation location identification section/floor/room: ................................................................................................................

 

Damper product type: .................................................................................................................................................................... 
Release fuse temperature: .............................................................................................................................................................. 

Notes/Considerations: ....................................................................................................................................................................

Installed by: ..................................................................................................................................................................................... 
Company Name: ............................................................................................................................................................................ 
Address: .......................................................................................................................................................................................... 
Company Telephone No: ............................................................................................................................................................... 
Installers Name: .............................................................................................................................................................................. 
Installers Telephone No: ................................................................................................................................................................. 
Date of installation: ........................................................................................................................................................................

It is hereby verified that the damper detailed above has been installed and tested according to the manufacturers 

recommendations:
Installers signature: ................................................................................................ 

Date: ................................................

Содержание Actionair SmokeShield PTC

Страница 1: ...nt supplier Actuators All wiring should be carried out in accor dance with the wiring details provided by the IEE and BS regulations and by a competent person Care must be taken when installing and inspecting dampers as they are likely to close without warning due to loss of electrical power or a temperature rise in the ductwork This is their prime function Do not insert any items fingers or limbs...

Страница 2: ... with fire separating elements to maintain fire compart ments The SmokeShield is an actuated failsafe close damper with low smoke leakage often referred to in the industry as a Fire Smoke damper Under the Fire Damper Product standard BS EN 15650 our Fire Damper products are tested to BS EN 1366 2 and classified under BS EN 13501 3 For smoke control the product you use should be tested to BS EN 121...

Страница 3: ...nto the interface shroud Do NOT fill above damper casing 6 When compound has fully set remove damper inter face transit plate and check the internal is free from any debris remove any debris 7 Follow the actuator installation procedure detailed in this document Comments Rev Drawn By M Bushell Approved By Kimberley M 1 Reference No Gore S Checked By AAF12368 Description If your proposed installatio...

Страница 4: ...d the damper casing making sure all the gaps are fully sealed as per industry standard 8 When the first layer has set pour in the next level to 100mm thickness IMPORTANT Compound must not be too watery or runny as it risks penetrating into the interface shroud do NOT fill above damper casing against penetration of compound into interface shroud 9 When compound has fully set remove the shutterbatt ...

Страница 5: ...n Both screws should be tightened fully to ensure that both sections of the ETR are closed together It is a safety feature if both sections are not closed the unit will not operate For ductless installations the ETR should be fitted onto the damper spigot not casing above the damper interface shroud and in accordance with the fitting instructions If the ETR is not fitted in the exact manner descri...

Страница 6: ...s A comprehensive example of the maintenance pro cedure is given in Annex D of the standard Some automatic systems may allow more frequent testing 48hr or less and this may be required by a national standard Approved Document B Volume 2 Clause 10 12 states adequate means of access must be provided to allow inspection testing and maintenance of both fire damper and its actuating mechanism BS 9999 2...

Страница 7: ...LY OPEN AC DC 230V 50 60 Hz 14 VA 12 4 W 30 C 50 C CONTINUOUS TF 72 C AC 250V 6 3 A N CONTINUITY WITH COMMON ELECTRICAL THERMAL RELEASE ETR MUST BE FITTED TO DUCTING FOR DAMPER OPERATION SPRING BIASED TEST SWITCH WHEN DAMPER CLOSED CONTINUITY WITH COMMON WHEN DAMPER OPEN CONTINUITY WITH COMMON WHEN DAMPER CLOSED CONTINUITY WITH COMMON WHEN DAMPER OPEN Supply Off Damper spring closes Mode 5 3P PTC ...

Страница 8: ...H WIDTHS AND HEIGHTS OF 200 1000MM FOR DUCT WIDTHS AND HEIGHTS OF 151 199MM FOR DUCT WIDTHS 200MM 1000MM WITH HEIGHTS OF 100 199MM Base Dampers Circular Dampers Series 601 For Circular and Flat Oval Dampers spigots are 3mm under duct size Diameters and flat oval diameters in 1mm increments Circular Dampers Series 601 FOR DAMPERS 100 150MM D FOR CIRCULAR AMPERS SERIES 601 DIAMETERS 151 199MM 2 FOR ...

Страница 9: ...red Check wiring in accordance with procedures The ETR cables have been damaged or tampered with Replace with new mode Control Mode operates but limited or no movement of damper blades is observed The mode is not correctly synchronised with the inter face Remove motor from interface Check motor in fully released state Set position of interface and refit motor with label upmost include motor locati...

Страница 10: ...pening will invalidate the installation method Damper installer to advise the lead contractor if problems are foreseen 8 Using the access opening provided check that blades open and close Check position of damper blades 9 Has the damper been checked for internal cleanliness free from damage and that vertical casings in particular are free from debris With the damper in the closed position inspect ...

Страница 11: ...11 20220811 L00009 1 2 Swegon reserves the right to alter specifications Actionair SPAN Installation Guide Notes ...

Отзывы:

Похожие инструкции для Actionair SmokeShield PTC