Model

STH-4KTL

-HT

STH-5KTL

-HT

STH-6KTL

-HT

STH-8KTL

-HT

STH-10KTL

-HT

STH-12KTL

-HT

Outside 

diameter (mm)

12-18

12-18

12-18

12-18

12-18

12-18

Conductor core 

section(mm²)

2.5-10

2.5-10

2.5-10

3.2-10

4-10

6-10

Breaker (A)

20

20

20

32

32

40

4.3.5.2 AC connector assembly procedures
The recommended AC cable and AC breaker for Sunways STH 4~12kW series three-phase 
hybrid inverter are as shown in the following table:

1) According to the table above, select an appropriate AC cable, peel off the insulation sleeve 
of AC cable for 40~60mm, and peel off the sleeve in the conductor core of 3L/PE/N wires for 
8mm, as shown in Figure 4-22:

2) Insert the stripped AC cables through the AC connector cover in the sequence as shown in 
Figure 4-23:

Strip Length:8mm

40-60mm

Wire Diameter:12-18mm

Cables

Screw cap The insulator AC sheet 

cover

BACK-UP

ON-GRID

Single hole

seal ring

Figure 4-25

Figure 4-26

Figure 4-24

3) Put the cord end terminals on the stripped conductors one by one and press with some 
pressure to make it tightly locked with the conductors, as shown in Figure 4-24:

4) Lock the well-pressed cord end terminals into the AC connectorin the accessory bag and 
make sure the cables sequence is in line with the mark on the connector, as shown in Figure 
4-25:

5) Insert the assembled AC connector to the corresponding AC port in the inverter, as shown in 
Figure 4-26:

The cold-pressed terminals must be locked tightly, and make sure it won’t 

be loose after a long period of use.

Caution 

Please distinguish the on-grid and back-up port, and don’t mix up the 

on-grid port and back-up port when making the connection.

Caution 

BACK-UP

ON-GRID

Содержание STH-10K-HT

Страница 1: ...1 Three phase High voltage Hybrid Inverter STH 4K 5K 6K 8K 10K 12KTL HT User Manual Ningbo Sunways Technologies Co Ltd...

Страница 2: ...e 16 3 4 Packing List 17 4 Product Installation 18 4 1 Selection of Installation Location 18 4 2 Mounting the Inverter 19 4 3 Electrical Connection 21 4 4 Communication Connection 34 4 5 Monitoring De...

Страница 3: ...n and maintenance 2 1 6 To use this grid connected inverter for power generation needs the permission of the local power supply authority 2 1 7 During the operation of the inverter the surface tempera...

Страница 4: ...e symbols displayed on the hybrid inverter nameplate and packing box 2 4 1 Symbols on the Hybrid Inverter Description Symbol Grid status indicator 2 4 2 Symbol on the Inverter nameplate The inverter c...

Страница 5: ...d below STH 4KTL HT STH 5KTL HT STH 6KTL HT STH 8KTL HT STH 10KTL HT STH 12KTL HT 3 1 3 Applicable grid type The applicable grid types of the Sunways STH 4 12kW series are TN S TN C TN C S and TT When...

Страница 6: ...in in if the battery is not enough Mode 2 In this working mode set the Pmax from grid in the App can realize the Peak Load Shifting When the loads consumption less than the Pmax loads are supplied by...

Страница 7: ...ge the battery in the predetermined period Inverter will use power from PV and battery to supply loads in the predetermined period and the insufficient part will be supplied by the grid No Grid No Gri...

Страница 8: ...ure 3 4 410mm 175mm Name Plate Logo Display 550mm 410mm Figure 3 5 Bottom view Figure 3 6 Inverter back view 3 2 3 Inverter bottom view as shown in Figure 3 5 3 2 4 Inverter back view as shown in Figu...

Страница 9: ...the display Red An alarm or fault is detected view the fault info on the display 5 Display On Display the inverter operation information Off Display off to save power press the button to wake up the d...

Страница 10: ...ectly to strong sunlight to prevent the power derating due to excessive temperature 4 The inverter should be installed in a place with shelter to prevent direct exposure to sunlight and rain 5 Install...

Страница 11: ...ning 4 3 Electrical Connection Danger hint A high voltage in the conductive part of the inverter may cause an electric shock When performing any installation on the inverter make sure that the AC and...

Страница 12: ...2 L1 CT C CT B CT A PV Strings Battery To Battery To Sunways Meter Power Meter Sunways Meter AC Breacker AC Breacker AC Breacker AC Breacker AC Breacker 1 phase Loads 3 phase Loads Loads FN Set Run Ac...

Страница 13: ...stem all inverters PE wire need to be connected to the same grounding copper bar to ensure equipotential bonding 4 3 2 External ground connection Ground terminal connection steps 1 The external ground...

Страница 14: ...o the corresponding positive and negative connectors pull back the cable to ensure that the terminal is tightly attached in the connector 6 Use an open end wrench to screw the nut to the end to ensure...

Страница 15: ...ered when making AC output connection 1 An independent AC breaker is required in both inverter on grid and back up output side and any loads cannot be connected with inverter directly 2 Before making...

Страница 16: ...ence as shown in Figure 4 23 Strip Length 8mm 40 60mm Wire Diameter 12 18mm Cables Screw cap The insulator AC sheet cover BACK UP ON GRID Single hole seal ring Figure 4 25 Figure 4 26 Figure 4 24 3 Pu...

Страница 17: ...S1 10 L3 S2 12 L Power supplied from 220V grid 13 N RS485 RS485 Communicate with inverter CT installation direction and phase sequence should strictly follow the instruction in the user manual otherw...

Страница 18: ...on bus interface EMS EMS power dispatching interface RLYOUT Dry contact output a group of normally open contact passive dry contact PARCAN EMS RLYOUT 4 4 2 Communication between inverter and meter The...

Страница 19: ...ake sure the battery you selected is in the battery approval list of Sunways otherwise the system may not work properly Please contact your installer or Sunways service team for confirmation if you re...

Страница 20: ...the installation represents that the assembly is in place 5 Start and Stop 5 1 Start Inverter When starting the inverter follow these steps 1 Turn the DC switch in the inverter bottom to the ON positi...

Страница 21: ...te and Local before starting the auto test Remote is set as 1 by default which only can be modified to 0 by sending an external command and Local is set as 0 by default which can be modified to 1 thro...

Страница 22: ...e installer or manufacture SPI Fault 1 Restart the inverter 2 Seek for help from the installer or manufacture E2 Fault 1 Restart the inverter 2 Seek for help from the installer or manufacture GFCI Dev...

Страница 23: ...5 Voltage Harmonic Distortion 3 LinearLoad Model STH 4KTL HT STH 5KTL HT STH 6KTL HT STH 8KTL HT STH 10KTL HT STH 12KTL HT Efficiency Max Efficiency 98 1 98 1 98 1 98 2 98 2 98 2 European Efficiency 9...

Страница 24: ...V1 01 EN Address No 1 Second Road Green Industrial Zone Chongshou Town Cixi City ZheJiang Province PEOPLE S REPUBLIC OF CHINA Website www sunways tech com Service Mail service sunways tech com Hotline...

Отзывы: