4 Commissioning
34
· The data for the individual slaves can be assigned
in the Sunways Browser and in the menu of the
master based on the IDs.
· The CAN-ID 1 is automatically assigned to the
master. This means the slaves can be assigned IDs
between 2 - 99.
· Commissioning cannot continue until an ID has
been requested from the master.
2. Completion of commissioning
Confirm overview with
.
3. Carry out commissioning for all other slaves as
described above.
Later commissioning
If you add new devices or replace existing ones in
your solar system, then you can display the device
list in the display on the master under «Settings –
Network – CAN bus». The new device can then be
put into operation in accordance with the descrip-
tion for commissioning slaves.