9. Level and stabilize Machine by placing a millwright's
level on ground Table Base
(see Figure 1-3)
. Machine
needs to leveled both from front to back and left to
right.
NOTE:
Machine does not need to be bolted to floor
but should be set on 1/2" thick steel pads.
• Begin by screwing ALL six (6) Adjustable Feet all
the way into the Table Base (until table base is resting
on the floor).
• Then check to see if any of the feet are not
touching the floor or touching the floor only
loosely. If so, bring foot down to just touch floor.
• Place Level front to back on right side of table and
adjusting Leveling Bolts in each of the right front &
rear feet as required, until table base is within
0,0003 m/m.
• Re-check and adjust any feet that are loose or not
touching, until they just touch the floor.
• Repeat for left side of table.
• Re-check and adjust any feet that are loose or not
touching, until they just touch the floor.
• Move to front of table and check front of table left
to right for level. Adjusting Leveling Bolt in which
ever of the feet is lowest as required, until table
base is within 0,0003 m/m.
• Adjust center Leveling Bolts at front of table until
it just touches the floor.
• Move to rear of table and check rear of table left
to right for level. Adjusting Leveling Bolt in which
ever of the feet is lowest as required, until table
base is within 0,0003 m/m.
NOTE:
In most cases the lowest foot should be on the
same side in the rear as the one that was just adjusted
on the front of the table.
• Adjust center Leveling Bolts at rear of table until it
just touches the floor.
• Recheck table front to back and left to right.
• Tighten Jam Nuts on all the feet to lock bolts in
place.
• After leveling Table Base using by adjusting the
feet; place shims under table base wherever the base
is not in direct connect with the floor.
NOTE:
This is very important. If Table Base is not
supported it may bowl when the weight of the fixture
and workpiece are installed.
10. ATTENTION - Remove steel Cross Bracket that
supports machine during shipping
(see Figure 1-4)
.
11. Adjust Leveling Bolts as required to level
machine.
12. Remove Upper Right & Left Guarding from
inside the front of the Machine
(see Figure 1-5)
.
Lay Guarding and Hardware aside for reinstallation
after Column is installed.
2
FIGURE 1-4, Shipping Brackets
CROSS
BRACKET
FIGURE 1-5, Upper Left & Right Guarding
LEFT
UPPER
GUARDING
RIGHT
SCREWS
SCREWS
FIGURE 1-3, Leveling Bolts
MILLWRIGHT’S
LEVEL
JAM NUT
LEVELING
BOLT
SHIM
SHIM
SHIMS
Содержание SV-2460
Страница 14: ...8 NOTES...
Страница 22: ...16 NOTES...
Страница 26: ...20 NOTES...
Страница 32: ...26 NOTES...
Страница 36: ...30 NOTES...
Страница 38: ...32 NOTES...
Страница 40: ...34 NOTES...
Страница 41: ...1 OF 2 C DECLARATION OF CONFORMITY 35 SAMPLE CE DOCUMENT...
Страница 42: ...2 OF 2 C DECLARATION OF CONFORMITY 36 SAMPLE CE DOCUMENT...