42
•
Incorrect connection sequence may cause fire. Pay maximum attention to the
connection sequence.
•
Ensure the firmness of the cable connection. Poor connection or oxidation of
the surface may cause over-heating or fire.
•
Long bolts may affect the insulation and may cause short circuit.
•
Remove the heat-shrink tubing between the cable lug and the copper bar if
necessary. Poor contact or over-heating may follow if otherwise.
step 6 Confirm that all cable connections are secure.
- - End
6.7
Communication Connection
The communication terminals are located in lower part of the intelligent PMD, as shown in
the figure below.
No.
Description
A
XB21 terminal blocks, RS485 communication port
B
Ethernet port
On site, perform cable connection according to internal terminal markings.
6.8
External Equipment Connection
The power distribution cabinet is divided into two versions: 5KVA and 35KVA. The actual MV
Station received may be equipped with one of these versions, and the specific agreement
shall prevail.
If 5KVA is chosen, please refer to
6.8.1 5KVA Power Distribution Cabinet
to perform the
connection.
If 35KVA is chosen, please refer to
6.8.2 35KVA Power Distribution Cabinet
to perform the
connection.