Open the Door of SG100K3
Use the following procedure to shut down the SG100K3 Inverter before servicing:
1. Stop the inverter from the LCD control menu.
2. Switch off the AC main switch (turn the switch to the “off” position)
3. Switch off the DC main switch (turn the switch to the “off” position).
4. Press in the handle to make it pop out from the lock hole, turn it right.
5. Now you can open the front door.
Warning
::
SShock Ha
azard
d
The terminals of the SG100K3 PV input may have energy when the PV arrays
are energized.
After shut down, wait a minimum 90 minutes should be left for all
capacitors of SG100K3 to discharge and left with no potential
Содержание SG100K3
Страница 1: ...S SG100K3 G Grid Connected Inverter Installation Manual SG100K3 3B E Ver65 200907 Version 6 5...
Страница 8: ...Safety Instructions Chapter 1 provides important safety instructions about SG100K3...
Страница 13: ...5 I Introduction Chapter 2 provides basic information about SG100K3...
Страница 34: ...26 Commissioning Chapter 5 describes the verification and commissioning of SG100K3...
Страница 37: ...29 Appendix...