Chapter 3
Facility and System Requirements
3-7
1. Ensure the customer has properly grounded PDUs in the data center. The PDU
must be earth ground.
2. Ensure all grounding points (raised floors and power receptacles) reference PDU
ground.
Note –
The customer needs to procure the grounding cable. A grounding cable is
not shipped with the system.
3. Attach the ground cable to the system, behind the kick plate, at the bottom of the
frame base as shown in
FIGURE 3-4
Ground Cable Attachment Point at System Cabinet
4. The ground cable attaching area might be a painted surface. Ensure metal-to-metal
solid contact is made for this installation.
System cabinet base
Ground cable
attachment point
Kick plate
Air filters
Содержание Sun Fire 12K
Страница 6: ...vi Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 8: ...viii Sun Fire 15K12K Systems Site Planning Guide June 2003...
Страница 10: ...x Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 14: ...xiv Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 28: ...1 14 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 44: ...3 8 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 60: ...A 2 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 64: ...A 6 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 66: ...A 8 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 68: ...A 10 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 70: ...A 12 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 72: ...A 14 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 74: ...A 16 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 76: ...A 18 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 78: ...A 20 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 80: ...A 22 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 82: ...A 24 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 83: ...B 1 APPENDIX B Compliance Statements...
Страница 84: ...B 2 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 96: ...B 14 Sun Fire 15K 12K Systems Site Planning Guide June 2003...
Страница 100: ...Index 4 Sun Fire 15K 12K Site Planning Guide June 2003...