2. When finish installing all arches, lift the arch to top of containers, and then adjust the distance
between arches. Weld the base plate to container firmly.
3. Install Purlin (No.5) by Carriage Bolt M10x80 (No.12) and then the third arch and Purlins. In this turn,
one arch and then purlin tubes.
4. Install Steel Wire (No.21) between arches by Tube Clip (No.10), Connection Plate (No.6), Turnbuckle
(No.19) and Steel Wire Clamp (No.20).

IMPORTANT: THE WIDTH OF ARCHES SHOULD BE ADJUSTED BEFORE LIFTING.

C—COVER INSTALLATION

NOTE: DO NOT install the cover onto the frame of your building in high wind conditions. A slight breeze
is the most advantageous for cover installation. To take advantage of the breeze, pull the cover up over
the arches with the breeze blowing in the cover like a sail filled with air.

1. Roll out the roof cover on a ground sheet. Align the cover evenly to each end of the frame. Be sure

doing not over pull the end of the roof cover.

2. Insert the Tensioning Tubes (No.9) into the cover pipe pockets. Pull the cover over the frame

EVENLY, CAREFULLY AND SLOWLY. Cut openings on the pocket above the corresponding base plate
and loosely secure the Belt (No.14) in the Winch (being installed on base plates). DO NOT TIGHTEN.
Adjust the cover so that it is square and evenly centered on the frame.

Note: The end flaps must overhang evenly at both ends.
3. Use Rope (No.15) to tighten roof cover to end arches. Rope should be cut as your requirements

when using. When the cover is tidy and ready, drive the winch tie down forth and back and then
roof cover is tightened. Pull the band inside the roof cover (four corners) by Winch on base plate
(No.7).

Note: if there is damage for cover when use, please repair it as soon as possible to avoid

further damage.

Содержание C4040DTR

Страница 1: ...1 Shipping Container Roof Double Truss Round Style Model C4040DTR 40 x40 x15 8 arch space Assembly Instructions...

Страница 2: ...2 Equipment List Speed Wrench 22 23 24 Hammer 30lb Rope 12 Long Tape 50m Hammer Drill 1 Lifter 2 Crane 1 Forklift 1 Protective equipment...

Страница 3: ...and damage LOCATION Choosing the proper location is an important step before you begin to assemble the structure The following suggestions and precautions will help you determine whether your selected...

Страница 4: ...steel into the hole making sure 3ft is below the surface completely laying on the side of the containers 3 Weld the square steel to the 2 containers 4 Pour cement in the holes to make sure the square...

Страница 5: ...of Single truss framing Customer responsibility 4 It s the owner s responsibility to shovel snow off the canopy rooftop 5 All containers need to be anchored to the ground in each opposite corner sides...

Страница 6: ...er Truss Arch 12 5 Purlin 35 6 Connection Plate for steel wire No 21 16 7 Base Plate four corners with winch 4 8 Base Plate inner with winch 8 9 Lower Tensioning Tube for Roof Cover 4 1 pcs set 2 sets...

Страница 7: ...7 13 End Plug 4 14 Belt for winch 12 15 Knitting Rope for roof cover 4 bundles 1 pack 16 Roof Cover 1 17 Duct Tape 2 18 Expansion Bolt 48 19 Turnbuckle 16 20 Steel Wire Clamp 32 21 Steel Wire 16...

Страница 8: ...er to the diagram Figure 1 to mark the position of base plates Figure 1 1 The measurement is done as the above figure 1 showing Referring to the above diagram and confirm the place of base plates ENSU...

Страница 9: ...9 B FRAME INSTALLATION 1 Arch Installation Find Truss Arches No 1 2 3 4 and Base Plate No 7 8 and connect them by Bolt M8x70 No 11 Purlins and Support Tubes...

Страница 10: ...a sail filled with air 1 Roll out the roof cover on a ground sheet Align the cover evenly to each end of the frame Be sure doing not over pull the end of the roof cover 2 Insert the Tensioning Tubes N...

Страница 11: ...11 Roof Cover Installation Now your assembly is completed...

Отзывы: