Close the isolating valve between the unit and system, and switch on the unit.  
 
The pump should run up to cut-out pressure, and stop.  
 
Crack open the system isolating valve, and observe the pressure gauge on the unit.  
 
Note the pressure at which the pump starts, and adjust this pressure if required to suit the system fill 
pressure determined from design data.  
 
Close the system isolating valve. 
 
Lower the pressure within the unit by draining away and note the pressure at which the system low 
pressure cut-out switch operates.  
 
Run the pump  thereby raising the pressure and note the pressure at which the system high pressure 
switch operates.  
 
Check that these pressures are correct, and that the burner / chiller shutdown contacts operate 
correctly. 
 
SEB200 units have an additional pump.  
 
On initial switch-on at low pressure, the standby pump will run to cut out pressure and stop, 
whereupon the duty pump will start and run to its cut-out pressure.  
 
On falling pressure, the duty pump will start at its cut-in pressure.  
 
Should this pump fail to start the pressure will continue to fall until the standby pump starts.  
 
Note that only one pump ever operates at one time. 
 
Open the valves to the system and switch on.  
 
The unit will run, if required, to bring the system up to the fill pressure.  
 
If the pressure in the system is already higher than the fill pressure, drain water from the system until 
the unit runs, then close the drain point, and allow the unit to switch off.  
 
This ensures that the correct fill pressure has been achieved. Commissioning of the unit is now 
complete. 
 
Please note that Stokvis cannot accept any warranty claims in respect of units which have not been 
commissioned in accordance with the above procedure, nor for units where the settings vary from our 
recommendations. 
 

 

 
 
 
 
 
 
 

Содержание ECONOPRESS EP 1

Страница 1: ...G UNITS INCLUDING H P UNITS OPERATING AND MAINTENANCE INSTRUCTIONS STOKVIS ENERGY SYSTEMS 96R WALTON ROAD EAST MOLESEY SURREY KT8 0DL TEL 08707 707 747 FAX 08707 707 767 E MAIL info stokvisboilers com...

Страница 2: ...2 Contents Contents 2 General Description 3 Storage 4 Installation 4 Unit 5 Commissioning 5 Maintenance 7 Spare and service 8 General data Error Bookmark not defined...

Страница 3: ...ressure the standby pump EP 2 units will start as the pressure falls further If the pressure within the system goes beyond preset design limits then the system pressure alarm switches will become acti...

Страница 4: ...ther on a smooth level surface or alternatively back fixed to a suitable wall or other vertical structure in areas which are dry well ventilated and free from any danger from frost Once the unit has b...

Страница 5: ...ctions Any parts removed for transit must be refitted The above in conjunction with the drawings should enable the unit to be installed ready for commissioning however if you require advice or assista...

Страница 6: ...al switch on at low pressure the standby pump will run to cut out pressure and stop whereupon the duty pump will start and run to its cut out pressure On falling pressure the duty pump will start at i...

Страница 7: ...p as indicated by the unit gauge Check that the switch resets before cold fill pressure is reached Close the valve between the unit and system and expansion vessels Run the pump raising the pressure a...

Страница 8: ...records of all units supplied General data EP1 EP1HP EP2 EP2HP FACTORY SETTINGS Duty pump cut in pressure 2 5 BAR 6 BAR 2 5 BAR 6 BAR Standby pump cut in pressure N A N A 2 3 BAR 5 8 BAR SE vessel pre...

Страница 9: ......

Страница 10: ......

Страница 11: ......

Страница 12: ......

Отзывы: