Mounting instructions for bouncing bridge „arcus“  

Item-No. 51 4512 401

State: 18.01.2021 p. 2

 

1.  Select the location of the play equipment taking into account the required 

minimum space (see diagram 3). 

2.  Carry out excavation work for the foundations as shown in diagram 2. After 

excavation compress the foundation floor.

 

Note: 

Pay attention to items marked „ground level“ at the equipment! 

3.  Set up the concrete foundations according to diagram 2 with central, horizon-

tal reinforcement.

4.  After a setting period of 10 – 14 days, depending on weather conditions and 

foundation size, fill up and compress the holes between the foundation and 

the foundation hole with excavation.

5. 

Clean the foundation surface. Set up the both tubular frames and secure 
them against falling over. Insert the both hanging pipes into the frames and 
fix them with the supplied screws.

6. 

Fix the bouncing bridge with the included shackles to the pipes above, and 
to the side of both tubular frames. To guarantee a permanent connection, we 
recommend gluing in the shackle bolts.

7. 

Align the equipment and screw the base plates of the equipment to the foun

-

dation using the included heavy-duty dowels. 

Reinforcement plan: 

Concrete foundation with reinforcement

Foundation: BSt 500S 
Stirrups Ø 8 mm lengthwise and cross 
Concrete cover h´= 3 cm
Concrete quality class C20/25

Diagram 2: Foundation plan

ground level

400

3778

450

2520

 400 

A

A

1100

500

1610

500

A-A

OHNE SCHRIFTLICHE ZUSTIMMUNG DER KAISER GMBH DARF DIESE 

TECHNISCHE UNTERLAGE WEDER VERVIELFÄLTIGT, NOCH DRITTEN MITGETEILT ODER 

ZUGÄNGLICH GEMACHT WERDEN, NOCH IN SONSTIGER WEISE MISSBRÄEUCHLICH VER- 

WENDET WERDEN. ZUWIDERHANDLUNGEN WERDEN URHEBERRECHTLICH VERFOLGT.

1

 

arcus

Benennung

Gepr.

Blatt

Datum

Projekt

Gez.

Zeichnungsnummer

1:25

A3

Name

Name

Fundamentplan

2129-00-00

Maßstab

Schramm

01.08.18

 

 

Gewerbegebiet Larsheck

56271 Kleinmaischeid

Deutschland

Beton

concrete
gewachsenes Erdreich

natural ground

Legende

stoßdämpfender Boden

shock-absorbing floor

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 
ES

11.01.21

beliebiger Boden

A

Datum

Änderung

Rev

beliebiger Boden

optional floor

Содержание arcus

Страница 1: ...rsheck D 56271 Kleinmaischeid Tel 49 0 2689 92790 0 All rights and product modifications reserved Mounting instructions for bouncing bridge arcus Item No 51 4512 401 State 18 01 2021 p 1 Diagram 1 Overall view of the play equipment ...

Страница 2: ... bridge with the included shackles to the pipes above and to the side of both tubular frames To guarantee a permanent connection we recommend gluing in the shackle bolts 7 Align the equipment and screw the base plates of the equipment to the foun dation using the included heavy duty dowels Reinforcement plan Concrete foundation with reinforcement Foundation BSt 500S Stirrups Ø 8 mm lengthwise and ...

Страница 3: ...nt shall not be used in such cases NOTE Play equipment which contain components made of stainless steel should not come with normal steel parts in contact Those steel parts may rub off and leave small steel particles in combination with moisture brown rust stains If such corrosion occur on stainless steel parts they are fine with an abrasive 240 grit to remove Please take care when transporting an...

Страница 4: ...uipment with wooden elements it cannot be ruled out that dry cracks may develop These natural changes of wood are dependent on clima te conditions as well as on the age and usage of the play equipment Longer dry periods may lead to more dry cracks This development however does not represent a quality defect Static properties of the equipment are not impaired See EN 1176 Bbl 1 2019 01 4 2 7 6 Dry c...

Отзывы: