1. Select the location of the play equipment taking into account the required
minimum space (see diagram 3).
2. Carry out excavation work for the foundations as shown in diagram 2. After
excavation compress the foundation floor.
Note:
Pay attention to items marked „ground level“ at the equipment!
3. Set up the concrete foundations according to diagram 2 with central, horizon-
tal reinforcement.
4. After a setting period of 10 – 14 days, depending on weather conditions and
foundation size, fill up and compress the holes between the foundation and
the foundation hole with excavation.
5.
Clean the foundation surface. Set up the both tubular frames and secure
them against falling over. Insert the both hanging pipes into the frames and
fix them with the supplied screws.
6.
Fix the bouncing bridge with the included shackles to the pipes above, and
to the side of both tubular frames. To guarantee a permanent connection, we
recommend gluing in the shackle bolts.
7.
Align the equipment and screw the base plates of the equipment to the foun
-
dation using the included heavy-duty dowels.
Reinforcement plan:
Concrete foundation with reinforcement
Foundation: BSt 500S
Stirrups Ø 8 mm lengthwise and cross
Concrete cover h´= 3 cm
Concrete quality class C20/25
Diagram 2: Foundation plan
ground level
400
3778
450
2520
400
A
A
1100
500
1610
500
A-A
OHNE SCHRIFTLICHE ZUSTIMMUNG DER KAISER GMBH DARF DIESE
TECHNISCHE UNTERLAGE WEDER VERVIELFÄLTIGT, NOCH DRITTEN MITGETEILT ODER
ZUGÄNGLICH GEMACHT WERDEN, NOCH IN SONSTIGER WEISE MISSBRÄEUCHLICH VER-
WENDET WERDEN. ZUWIDERHANDLUNGEN WERDEN URHEBERRECHTLICH VERFOLGT.
1
arcus
Benennung
Gepr.
Blatt
Datum
Projekt
Gez.
Zeichnungsnummer
1:25
A3
Name
Name
Fundamentplan
2129-00-00
Maßstab
Schramm
01.08.18
Gewerbegebiet Larsheck
56271 Kleinmaischeid
Deutschland
Beton
concrete
gewachsenes Erdreich
natural ground
Legende
stoßdämpfender Boden
shock-absorbing floor
ES
11.01.21
beliebiger Boden
A
Datum
Änderung
Rev
beliebiger Boden
optional floor