CheCklist
6
| WPL A | WPL AC | WPL AS | WPL ACS
www.stiebel-eltron.com
Checkpoint
Reference to the operat-
ing and installation in-
structions
Check-
box
Electrical installation
Have cables with a sufficient cross-section and the correct fuse
protection been used for the electrical connection?
-
- Compressor (outdoor unit)
-
- Controller (outdoor unit)
-
- Electric booster heater (outdoor unit or indoor unit)
- Controller (indoor unit or WPM)
Heat pump: “Preparing the elec-
trical installation”, “Data table”
Indoor unit: See the relevant
chapter
Has the indoor unit or WPM been connected to the outdoor unit
with the correctly screened cable? (J-Y (St) 2 x 2 x 0.8 mm²)
Heat pump: Chapter "Preparing
the electrical installation"
WPM controller: Chapter "Elec-
trical connection"
Has the cable screen been terminated at one end?
Heat pump: Chapter "Electrical
connection / WPL…"
Has the outside temperature sensor been installed on the correct
side of the building (north or north-east wall) and protected from
external heating and direct insolation?
WPM controller: Chapter “Sen-
sor installation”
With a mounting bracket, T-support or wall bracket: Has a ribbon
heater been laid in the condensate drain pipe to prevent the con-
densate from freezing?
Heat pump: Chapter “Ribbon
heater”
If cooling is to be provided: Have the room based remote controls
been installed in the lead room and connected electrically?
WPM controller: "FE7 remote
control", "FEK remote control",
"FET remote control"
For systems with a DHW cylinder: Has the DHW sensor been cor-
rectly positioned and connected?
WPM controller: Chapter "Elec-
trical connection", "Sensor in-
stallation"
For systems with a buffer cylinder: Has the buffer sensor been
correctly positioned and connected? (lowest sensor well in the
buffer cylinder)
WPM controller: Chapter "Elec-
trical connection", "Sensor in-
stallation"
If using a hydraulic module with buffer cylinder: Has the sensor
been correctly positioned in the heat pump return?
HM hydraulic module: Chapter
"Sensor installation"
Initial start-up
Has the correct language been set?
WPM 3 controller: Chapter
"COMMISSIONING" (LANGUAGE)
WPMsystem controller: Chapter
"SETTINGS" (GENERAL / LAN-
GUAGE)
If initial screed drying is required, start the heat-up program in
accordance with the screed contractor’s specifications.
Heat pump: Chapter "Initial
start-up / Using the heat-up
program"
WPM controller: Chapter "PRO-
GRAMS" (HEAT-UP PROGRAM)
Has the set room temperature been selected?
WPM controller: Chapter "SET-
TINGS" (HEATING / HEATING
CIRCUIT / COMFORT TEMPERA-
TURE and ECO TEMPERATURE)
Has the heating curve been set?
WPM controller: Chapter "SET-
TINGS" (HEATING / HEATING
CIRCUIT / HEATING CURVE RISE)
For systems with a buffer cylinder: Has the BUFFER OPERATION
parameter been set to “ON”?
WPM controller: Chapter "SET-
TINGS" (HEATING / STANDARD
SETTING / BUFFER OPERATION)
Has the dual mode temperature for heating been set?
WPM controller: Chapter "SET-
TINGS" (HEATING / EXTERNAL
HEAT SOURCE and ELECTRIC
REHEATING)