SPX SGS REFRIGERATION STC Series Скачать руководство пользователя страница 18

18 

operation

8.0 OPERATION

8.1 PRE-START UP 

After the installation is completed, a review of the following items 
should be preformed before the system is placed into operation: 
A.  Check electrical connections, fan bushing set screws, motor 

mount bolts, coil flange bolts, drain pan flange bolts, and 
all other fasteners for tightness. If required, be sure the 
thermostatic expansion valve bulb is properly located, strapped, 
and insulated.

B.  For systems with a defrost time clock check the timer to see 

that it is set for the correct time of day and the starting pins 
have been installed (normally two or three sets per day). 
Defrost should be scheduled when the freezer doors are not 
likely to be open.

C.  When the unit is first started the room temperature is typically 

above the contact closing temperature of the fan delay 
thermostat, if a fan delay thermostat is provided for Electric 
Defrost units (see that particular units electrical diagram). The 
fans may remain off for a lengthy period of time. To prevent 
this delay it is permissible to install a temporary jumper wire 
between terminals “1R” and “2B”. Once the room temperature 
is below 25°F the jumper wire should be removed.

D.  The motors for STC units are greased from the motor 

manufacturer.

8.2 OPERATION CHECKOUT 

With the system operating, check the supply voltage. The voltage 
must be /- 10% of the voltage marked on the unit nameplate 
and the phase to phase unbalance should be 2% or less. 
LISTEN CAREFULLY to the unit to make sure there are no unusual 
sounds. Sounds such as a noisy motor, the fan(s) scraping on the 
housing, or loose fasteners allowing parts to rattle need to be 
addressed immediately before continued unit operation. 
Check the room THERMOSTAT setting. Be sure it functions properly. 
For RECIRCULATED refrigeration systems the hand expansion 
valve should be opened slowly until either condensate or frost 
forms on the return bends from the bottom to the top of the coil. 
A good indicator is when the defrost relief valve reads 5 PSI above 
suction pressure. 
For FLOODED refrigeration systems check to make sure the float 
valve is working properly and allows refrigerant into the drum to 
the appropriate level when the level is sufficiently low. If a hand 
expansion valve has been added, the valve should be set to allow 
liquid make up 70% of the time. 

For DIRECT EXPANSION systems let the system balance out 
at the desired room temperature and check the operation of 
the expansion valve by properly measuring the superheat at the 
sensing bulb. As much as thirty minutes may be required for the 
new balance to take place after an adjustment is made. 
For BRINE or WATER COOLING systems keep the closest vent 
to the coil open while the fluid fills the coil to allow trapped air to 
escape. Close the vent valve once fluid flows out of the valve and 
check for water hammer in the coil. 
With HOT GAS DEFROST systems allow the coil to frost, then 
manually advance the defrost timer to initiate a defrost cycle. 
Observe the defrost cycle to see if all controls are functioning 
properly and that the coil is clear of all frost before the system 
returns to refrigeration. Adjust the time clock pins if necessary. 
Reset the defrost timer to the correct time of day. A defrost cycle 
is only needed when the frost build up is such that it impedes 
the airflow through the coil. The defrost requirements will vary on 
each installation and may change depending on the time of the 
year and other conditions..
With ELECTRIC DEFROST systems allow the coil to frost then 
manually advance the defrost timer to initiate a defrost cycle. 
Observe the defrost cycle to see if all controls are functioning 
properly and that the coil is clear of all frost before the system 
returns to refrigeration. Adjust the time clock pins if necessary. 
Reset the defrost timer to the correct time of day. A defrost cycle 
is only needed when the frost build up is such that it impedes 
the airflow through the coil. The defrost requirements will vary on 
each installation and may change depending on the time of the 
year and other conditions. 

Содержание SGS REFRIGERATION STC Series

Страница 1: ...STC Series twin unit cooler INSTALLATION OPERATION MAINTENANCE E329630 ISSUED 02 2020 READ AND UNDERSTAND THIS MANUAL PRIOR TO OPERATING OR SERVICING THIS PRODUCT user manual SGS REFRIGERATION...

Страница 2: ...Interpiping 8 6 4 Evacuation and Leak Test 8 6 5 DXA And Suction Accumulators 8 7 Electrical 9 7 1Field Wiring 9 7 2Electrical Data 9 7 3Suggested No Defrost Requirement Sequence of Operation 17 7 4S...

Страница 3: ...ocate the expansion valve bulb on a horizontal length of suction line closer to the connection stub Position the bulb in a 3 4 8 or 9 o clock position Do not position the bulb on the top or the bottom...

Страница 4: ...ould be in place before the unit is hung See Sections 2 3 and 2 4 The unit must be level in all directions to insure proper drainage of the condensate drain pan FIGURE 1 Unit Dimension 15 75 5 25 LENG...

Страница 5: ...00 64 00 24 00 94 00 59 75 8 115 00 70 00 24 00 94 00 65 75 30 4 133 00 62 00 28 00 112 00 57 75 68 68 6 133 00 70 00 28 00 112 00 65 75 8 133 00 76 00 28 00 112 00 71 75 Four 24 4 145 00 56 00 24 00...

Страница 6: ...m moist air from migrating through the drain line The trap should be located in the warmest and or lowest section of the piping to avoid freezing and provide sufficient liquid head for flow through th...

Страница 7: ...gnized refrigeration standards Under no circumstances should the refrigerant connection size of the unit be used as the basis for sizing the lines For aluminum flange connections see Figure 4 for fina...

Страница 8: ...4 EVACUATION AND LEAK TEST Whenallrefrigerationconnectionshavebeencompleted theentire system must be tested for leaks and then evacuated 6 5 DXA AND SUCTION ACCUMULATORS DonotuseunitswithDirectExpans...

Страница 9: ...3 5 2 5 Two 1140 1 3 3 6 1 8 1 8 1140 1 2 4 8 2 4 2 4 2 0 850 1 2 5 2 2 6 2 6 2 6 1140 3 4 5 6 2 8 2 8 2 4 850 3 4 8 0 4 0 4 0 3 2 1140 1 7 2 3 6 3 6 3 0 850 1 8 4 4 2 4 2 3 6 1140 1 1 2 10 0 5 0 5 0...

Страница 10: ...0 575 3 60 1 2 3 G 1 2 3 G 1 2 3 G 1 2 3 G 1 2 3 G 1 T2 T1 T3 2 3 G GRN FAN MOTORS 3 PHASE FAN MOTOR CIRCUIT TERMINAL BLOCK INSIDE UNIT 1 3 G 1 3 G 1 3 G 1 3 G 1 3 G 1 T2 T1 T3 3 G GRN FAN MOTORS SING...

Страница 11: ...HEATER CIRCUIT 2 HEATER CIRCUIT 3 HEATER CIRCUIT 4 2 B 1 R 4 Y 1 R 2 B 4 Y ADJUSTABLE DEFROST CONTROL MOUNTED ON BEND END OF UNIT ELECTRICAL ENCLOSURE BEND END OF UNIT JUMPER BLOCK INSIDE UNIT 4 PLAC...

Страница 12: ...CONTROL CIRCUIT HEATER CIRCUIT 1 HEATER CIRCUIT 2 HEATER CIRCUIT 3 HEATER CIRCUIT 4 2 B 1 R 4 Y 1 R 2 B 4 Y ADJUSTABLE DEFROST CONTROL MOUNTED ON BEND END OF UNIT ELECTRICAL ENCLOSURE BEND END OF UNIT...

Страница 13: ...2 58 27 35 27 35 42 58 34 06 STC4 43 A STC4 44 A 4 20 00 28 26 28 26 31 91 26 36 21 09 STC4 63 A STC4 64 A 4 28 00 35 79 35 79 43 32 35 79 28 63 STC4 83 A STC4 84 A 4 36 00 47 08 47 18 29 66 29 66 47...

Страница 14: ...C 3 32 60 42 00 43 83 26 78 26 78 42 00 33 60 STC3 46 C 3 25 40 32 49 32 49 39 33 32 49 25 99 STC3 66 C 3 39 80 31 45 17 61 31 45 17 61 32 25 32 25 26 64 26 64 40 83 STC3 86 C 3 47 00 39 72 21 65 39...

Страница 15: ...25 13 80 STC3 66 A 3 18 00 45 18 27 35 22 59 18 07 STC3 86 A 3 24 00 33 89 33 89 41 02 33 89 27 11 STC4 43 A STC4 44 A 4 16 00 41 48 27 35 22 59 18 07 STC4 63 A STC4 64 A 4 16 00 41 48 27 35 22 59 18...

Страница 16: ...0 27 11 27 11 32 82 27 11 21 69 STC3 83 C STC3 84 C 3 28 80 38 43 38 43 46 52 38 43 30 74 STC3 46 C 3 21 60 27 11 27 11 32 82 27 11 21 69 STC3 66 C 3 28 80 38 43 38 43 46 52 38 43 30 74 STC3 86 C 3 36...

Страница 17: ...H The defrost timer energizes the liquid line solenoid valve allowing refrigerant to flow into the unit cooling the coil and refreezing any remaining condensate drops that are still present I The fan...

Страница 18: ...tor is when the defrost relief valve reads 5 PSI above suction pressure For FLOODED refrigeration systems check to make sure the float valve is working properly and allows refrigerant into the drum to...

Страница 19: ...e any work is performed Remove the fan guard as described in Section 9 3 Loosen two bolts from the bushing that hold the fan onto the motor shaft Remove the fan Clean and deburr the motor shaft if nec...

Страница 20: ...315562 850 1 2 E315550 E315540 E315574 1 30 36 BC E315563 850 3 4 E315551 E315541 E315575 1 30 36 BD E315564 850 1 E315552 E315542 E315576 1 30 36 BE E315565 850 1 5 E315553 E315543 E315577 Table 8 Co...

Страница 21: ...ntenance Date Performed Drain Pan Inspection and Cleaning Cabinet and Coil Inspection and Cleaning Motor Inspection Fan Inspection Electric Heater Inspection Water Defrost Pan Inspection 11 MAINTENANC...

Страница 22: ......

Страница 23: ......

Страница 24: ...ERVED In the interest of technological progress all products are subject to design and or material change without notice SPX COOLING TECHNOLOGIES INC 7401 WEST 129 STREET OVERLAND PARK KS 66213 USA 91...

Отзывы: