31
Control Unit
CU4 Direct Connect
Instruction Manual: UK-3
Control Unit CU4 Direct Connect UK-3 / 20.04.2011
UK
APV
8.
CU Assembly and Start-up
lever
solenoid valve
8.3.3. Connection of external proximity switches
The electric connection of the proximity switches specified by
APV is undertaken according to the terminal layout described in
chapter 6.1.
The mechanic assembly of the proximity switches is carried out
at the actuator of the corresponding double seat valves.
Observance of the operating manual for double seat valves
is essential!
8.3.4. Start-up
After proper assembly and installation of the control unit, start-up
can be undertaken as described below:
1.
Switch on the air supply.
2.
Switch on the voltage supply.
3.
Check the solenoid valves by turning the handle on the upper
side of the valve by 90°.
4.
Check the valve position indicator.
The proximity switches are installed at the double seat valves
with a mechanical stop.
Adjustment is not required!
The following allocation applies for double seat valves:
Closed valve position feedback – sensor 1 controlled
Open valve position feedback – sensor 2 controlled
Check the proper fit of the proximity switches to provide for
the accurate transfer of the signals for the corresponding
valve position.