Installation
5.1
Unpacking the machine
Check that the machine instruction manual is in the document holder attached to the machine.
The operator’s manual should be regarded as part of the machine. Suppliers of both new and second-hand machines
are advised to retain documentary evidence that this manual was provided with the machine. Check that the serial
number has been entered inside the front cover of this manual. Add it appropriately if necessary. The serial number
plate is fixed to the main mower deck mower to the linkage mounting. Always quote these numbers in any
correspondence with a dealer.
5.1.1
Lifting the machine
WARNING!
Only personnel experienced in lift and hoist operation should be involved in lifting machines.
The approved lifting points are illustrated in the machine general specification section in chapter 1
–
‘Machine description’. Check that the correct lifting points are used to suit the machine's
configuration, as the centre of gravity will change if for example a side shift position or wing
deployment position is different per lift. - Exercise caution!
Use only the approved lifting points shown, and marked on the machine with the lifting decal, see
Figure 5.1. Also ensure any lifting equipment is capable of lifting the machine mass indicated in
Section 1.4 Machine general specification.
Figure 5.1
WARNING:
Only use approved lifting equipment which is correctly fastened to the machine - this will increase
your personal safety. Failure to follow the safety instructions could result in accidents and serious
injuries.
WARNING:
Before attempting to access the underside of the machine, ensure it is adequately and safely
supported. Do not rely on th
e tractor’s hydraulics. Use safety supports that are capable of supporting
the machine mass indicated in Section 1.4 Machine general specification.
On despatch from the factory the rotors and blades of the machine will be secured with restraining wires and/or cable
ties to stop them moving during delivery; these restraining wires must be removed before using the machine.
Locate and remove the
‘Power Take-off Shaft’ (PTO) from its shipping position, and temporarily store it in a place of
safety.
If fitted, remove the stacking transport legs, see Figure 5.2a.
With the machine suitably supported, remove all rotor and blade restraining wires and/or ties, see Figure 5.2b. Inspect
the underside of the machine to ensure it is undamaged, and check all blades rotate freely and do not foul on the body.
Figure 5.2
Blade
restraining
wires
Stacking
transport