Site Preparation Guide
TRAK DPMSX5P
Lifting and/or Moving the
Machine
Method 2
(see Figure)
:
1.
Insert 2 steel bars 1" dia x 36" long
through both sides in the existing holes
in the machine base (front and back).
2.
Position 4 (two each side) wood vee
blocks under the steel bars and over a
suitable lift truck.
3.
Lift the machine up (somewhat tilted
towards the front) 4-6" from the ground
and move it to its floor plan position.
WARNING!
The lift truck must have sufficient lifting
capacity (3 tons) and be equipped with
suitably long forks.
4.
Insert the 6 screws for the leveling pads
in their place in the bed.
5.
Place the machine in its location (see
floor plan bed/footprint) carefully
positioning each leveling pad under each
leveling screw.
Method 2
F16467-37 rev 051317
Page 4 of 4
Southwestern Industries, Inc.
2615 Homestead Place
Rancho Dominguez, CA 90220-5610 USA
T | 310.608.4422
|
F | 310. 764.2668
Service Department: 800.367.3165
e-mail: [email protected] | [email protected] | web: southwesternindustries.com
Содержание TRAK DPMSX5P
Страница 2: ......