![Southwestern Industries TRAK DPMSX5P Скачать руководство пользователя страница 4](http://html1.mh-extra.com/html/southwestern-industries/trak-dpmsx5p/trak-dpmsx5p_site-preparation-manual_1337635004.webp)
Lifting and/or Moving the
Machine
CAUTION!
The DPMSX2, SX3 & SX5 machines weigh
approximately 3200, 4100 and 4400 lbs. respectively.
Proper equipment of sufficient capacity must be used
when lifting and/or moving the machine.
Method 1:
1.
Insert a steel bar 1.0" dia x 36" long through the rear
side holes of the bed (under column)
.
2.
Use a steel cable (with protective sleeving)
min. 3/4" dia. or a 3 ton sling.
3.
Use cardboard pieces or other suitable
protective sheets on both sides of the machine
to prevent scratching.
4.
Remove the 4 nuts and screws holding the
machine to the wood skid.
5.
Lift the machine (the front side of the machine
should be lower than the back side).
6.
Insert the 6 screws for leveling pads in their
place in the bed. 4 screws for DPMSX2.
7. Place the machine in its location (see floor plan
and bed footprint drawing) carefully positioning
each leveling pad under each leveling screw.
8.
Remove the lifting cable or sling, the steel bar
and all protective cardboard.
Method 1
Site Preparation Guide
TRAK DPMSX5P
F16467-37 rev 051317
Page 3 of 4
Southwestern Industries, Inc.
2615 Homestead Place
Rancho Dominguez, CA 90220-5610 USA
T | 310.608.4422
|
F | 310. 764.2668
Service Department: 800.367.3165
e-mail: [email protected] | [email protected] | web: southwesternindustries.com