Installation Guide
Page
16
of
26
Opening the enclosure of the sonnenProtect-Plus
Use the lever provided in the accessories kit to open the enclosure door. Insert a small
screwdriver into the notches to unclick and remove the covers.
Before starting the wiring process of the sonnenProtect-Plus, switch off all the circuits to the
property.
Drilling through the enclosure must be performed at high speed with low pressure applied.
1-
Drill through the enclosure to insert gland entries. Drilling holes must be performed
at high speed while applying low pressure to ensure that the IP rating of the
enclosure (IP66) is retained.
•
It is recommended to remove the frame prior drilling through the enclosure
to avoid contamination of the electrical equipment.
•
Cable glands must be provided by the installer.
2-
Locate the incoming main AC supply from the grid and connect it directly into the
“Grid Supply”
labelled snap connectors in the sonnenProtect-Plus. These connectors
can take up to 16 mm CSA cables.
3-
Connect the normal loads into the
“Normal Loads”
labelled snap connectors in the
sonnenProtect-Plus. These connectors can take up to 16 mm CSA cables.
4-
Connect the essential loads into the
“Backup Loads”
labelled snap connectors in the
sonnenProtect-Plus. These connectors can take up to 10 mm CSA cables.