7. COMMISSIONING
7.1 Commissioning regulations
Commissioning and maintenance work must only be carried out by trained personnel.
Only work on the unit when it is at zero volt.
According to EN 50110-1 (VDE 0105-1), only qualified electricians may carry out the installation and
commissioning of the ventilation control unit and connected accessories.
Observe all regulations stipulated by your local power supply utility and all VDE regulations.
DIN VDE 0100 regulations regarding the installation of high voltage systems up to 1000 V
DIN VDE 0105-100 Operation of electrical installations
Only original Solid Air accessories may be used (electric coils, servomotors, etc.), otherwise Solid Air cannot
accept any liability.
Before commissioning, check whether the operating data specified on the type plate is adhered to.
The unit must not be operated before all necessary safety equipment has been fitted and connected. Intake
and discharge apertures must be connected to ensure contact protection. The CPL-C-WRG unit must be level
and safely secured.
Commissioning must be carried out by authorised personnel (Solid Air Customer Service).
Record the date of commissioning, e.g. in a log book.
According to DIN 1886, tools must be used to open the unit. Wait for the fans to come to a complete standstill
before opening the inspection doors. When opening the doors, negative pressure may draw in loose objects,
which could damage the fan irreparably or even cause a risk to life if items of clothing are drawn in. Use tools
to tightly seal the doors before commissioning (unit tightness).