Equipment grounding tightening torques: 4-6 AWG: 45 lb-in, 8 AWG: 40 lb-in, 10-14
AWG: 35 lb-in.
To allow for heat dissipation, maintain clearance as specified below.
All Power Optimizers, except for the P860 and P960 Power Optimizers
P860, P960 and M1600 Power Optimizers
Figure 3: Power Optimizers clearance
When installing PV modules in a confined space such as Building-integrated
photovoltaic (BIPV) modules, ventilation measures may be required to ensure that
the Power Optimizers are not exceeding the maximum temperatures stated in their
specifications.
Chapter 2: Installing the Power Optimizers
21
Three Phase Inverter with Synergy Technology P/N: SExxK-xxxxIxxxx SExxK-xxxxIxxxx