HEATER UNIT
GRILLE
T-BAR
HANGING
BOLT
HANGING
BOLT
TILE
T-BAR
TILE
Commissioning
Ensure the central heating system is
ON
. Providing the water temperature in the central heating
system is more than 35°C and the thermostat (if fitted) is calling for heat the product will switch on.
1) Turn on the electrical supply to the unit at the fused spur.
2) Turn on the central heating system.
3) Turn the thermostat control (if fitted) to the maximum.
4) If the heater is installed on the same circuit as panel radiators balance the central heating
system.
5) Adjust the fan speed to the preferred setting by adjusting the controller (turn left to reduce speed
and right to increase)
6) If the installation is working correctly remember to reset the thermostat control (if fitted) to its
normal setting.
If your heater does not operate refer to
“Fault Finding” on page 7.
Maintenance
Warning! Isolate from the electrical supply before servicing.
The heater is fitted with a replaceable air filter. To remove the filter lower the hinged grille, loosen
the two screws securing the filter retainer (See Figure 1), slide the across to give access and
remove the filter, replacing the air filter is the reverse of removing it. The filter can be gently tapped
or vacuumed to remove any accumulated dust. Replacement filters should be fitted as part of
regular and routine maintenance.
The filter is not covered by Smith’s 5 Year Guarantee.
The heat exchanger should be cleaned with a soft brush or vacuum to remove any dust that may
have accumulated, care must be taken not to damage the delicate heat exchanger fins.
The fan(s) and motors should not require servicing. Please contact your supplier if damaged.
Please note in the event of an engineer’s visit, Smith’s Environmental Products Ltd reserve the
rights to apply a call-out charge should the fault prove to be with the system or installation and not
the heater appliance.
6
Preparation
The following items should be included in the carton:
Caspian Skyline
®
CT60 EC unit.
Grille.
Installation & User Guide.
X4 No 8 Screws.
Other items required for a successful installation:
Three core mains cable.
Isolating valves (Failure to fit isolating valves may mean that the product is not serviceable
in the event of failure).
Air Vent/ Bleed valve.
Suitable mounting hardware (Such as chains, threaded rod etc).
Accessories including replacement air filters are available (See page 7).
In the event of any items missing or visible damage, please contact us on 01245 324560,
before continuing with the installation.
Installation
This heater should be mounted at a minimum height of 1.8m (To the underside of the grille) and a
maximum height 4m
Installation into a suspended T Bar ceiling
Figure 2
1)
Choose the position in the ceiling grid that the heater is to be installed and remove the
chosen ceiling tile, as well as any surrounding tiles to provide adequate access during
installation.
2)
Ensure suitable means of support such as threaded rods or chains are used and fixed into
place directly above the chosen grid position.
3)
Lift the heater through the T bar grid into the void and securely attach the supports to the
heater.
4)
Lift the grille into the grid and adjust the heater so that they meet together.
5)
Drill four holes (two in each side) 3mm
(1/8”) holes and secure with the provided screws
(See fig. 4). Once secured the grille can be opened and closed by pushing against the
grille on the side with the closure (Once to open, Once again to close), care should be
taken not to bend the grille.
6)
Proceed to page 5 for plumbing and electrical connection.