9.11 Deactivating Grounding Conductor Monitoring
If the inverter is to be installed in an IT network or another grid configuration in which deactivation
of the grounding conductor monitoring is required, deactivate the grounding conductor monitoring
as follows.
The basic procedure for changing operating parameters is explained in another section (see
Section 9.1 "Changing Operating Parameters", page 53).
Procedure:
• In the parameter group
Grid monitoring > Grid monitoring > Country standard
set the
parameter
PE connection monitoring
to
Off
.
9.12 Configuring Feed-In Management
If required by the grid operator, the inverter can provide grid management services. You can
configure these via the inverter feed-in management. Coordinate the configuration of the feed-in
management with your grid operator beforehand.
The basic procedure for changing operating parameters is explained in another section (see
Section 9.1 "Changing Operating Parameters", page 53).
Procedure:
1. Activate the user interface (see Section 8.1, page 44).
2. Log into the user interface as an
Installer
.
3. On the right-hand side of the menu bar, select the menu
User Settings
(see Section 8.3 "Start
Page Design of the User Interface", page 49).
4. In the subsequent context menu, select [
Start the installation assistant
].
5. Select [
Save and next
] until you arrive in the menu
Feed-in management
.
6. Configure the feed-in management as desired.
9 Configuration of the Inverter