2-1
FM 456-2 Application Function Module Installation, Hardware, and Startup
C79000-G7076-C458-01
Installation and Startup
This section provides you with some brief information about the necessary steps to
start up an FM 456-2.
The startup activities can be divided into several steps, which should be carried out
in the order shown:
1. Installing and switching on the hardware
2. Load operating system, adapt BIOS setup if necessary
3. Load user software into the FM 456-2 from PG/PC, test and commission. Adapt
S7/M7 software to the FM 456-2 functions.
The activities you must carry out in step 1 of the startup process are shown below
in the correct order in form of a checklist. The checklist contains notes on where
you can find detailed information on each point.
Refer to
manuals /2/ and /3/ for information on activities in steps 2 and 3 of the
startup process.
In this Chapter
Section
Subject
Page
2.1
Installation Checklist and Switch-on Test
2.2
Module Accessories
2.3
Installing Interface Submodules
2.4
Installing a Short AT Card
2.5
Fitting Expansion Modules to an FM 456-2
2.6
Installing a Module Assembly in the Module Rack
2.7
Inserting/Removing the Memory Card
2.8
Connecting a Module Assembly
2.9
Preparing for Operation
2.10
Connecting the Operator Panels and Peripherals
2.11
Connecting a Programming Device or PC to the COM Interface
2.12
First Switch-On of the FM 456-2