15
Introduction
This portion of the manual covers the
receiving, handling and storage instructions
for type SDR vacuum reclosers. This section
of the manual is intended to help the user
identify, inspect and protect the recloser
prior to its installation.
Receiving procedure
Make a physical inspection of the shipping
container before removing or unpacking the
recloser. Check for shipment damage or
indications of rough handling by the carrier.
Check each item against the manifest to
identify any shortages.
Shipping damage claims (when
applicable)
Follow normal shipment damage
procedures, which should include:
1. Check for visible damage upon arrival.
2. Visible damage must be noted on
delivery receipt and acknowledged with
driver‘s signature. Notation “Possible
internal damage, subject to inspection”
must be on delivery receipt.
3. Notify the Siemens field service at
+1 (800) 347-6659 or +1 (919) 365-
2200 outside the U.S.
4. Arrange for carrier‘s inspection. Do not
move the unit from its unloading point.
Handling procedure
1. Carefully remove the packing material
from the recloser. Keep the shipping
pallet for later use if the recloser is to be
stored prior to its installation.
2. Inspect for concealed damage.
Notification to carrier must take place
within 15 days to assure prompt
resolution of claims.
3. The recloser should be appropriately
lifted to avoid damaging the recloser.
4. The palleted recloser can also be moved
using a properly rated forklift vehicle.
The pallets are designed for movement
by a standard forklift.
Receiving, handling
and storage
Heavy weight.
Can result in death, serious injury or property damage.
Obtain the services of a qualified rigger prior to hoisting the recloser
switch unit to assure adequate safety margins in the hoisting
equipment and procedures to avoid damage.
Содержание SDR 15.5 kV
Страница 39: ...39 ...