Commissioning
6
Localization and device testing
29
Building Technologies
A6V10374021_c_en_--
Fire Safety
2014-07-01
6 Commissioning
The device is commissioned via the control panel. The exact procedure is
described in the control panel documentation.
Conduct a performance check once commissioning is complete.
6.1 Localization and device testing
The manual call points have an internal alarm indicator. This internal alarm
indicator may also be activated from the control panel for localization and device
testing.
The LED indicator of the alarm indicator has the following meanings::
LED indication
Meaning
Off
Normal condition
Green
Flashes once per second
Test mode is active
Red
Flashes once per second
Localization is active
o r
Alarm is triggered
Red and green alternating
Flashes twice per second
Alarm is triggered/localization is active
a n d
Test mode is active