As such, you can determine whether the machine needs commissioning or any necessary
measures such as cleaning and/or drying the winding:
● Can the machine be put into operation?
● Must the windings be cleaned or dried?
Detailed information on testing and the limit values can be found here:
"Testing the insulation resistance and polarization index" (Page 41)
8.7
Decommissioning the machine
● Record the decommissioning steps. This log will be useful upon recommissioning.
● If the machine is going to be out of service for longer than six months, then take the
necessary measures for preservation and storage. Otherwise, the machine could be
damaged as a result of not being operated.
See also
Protection against corrosion (Page 38)
Securing the rotor (Page 31)
Storage (Page 33)
8.8
Re-commissioning the machine
When you re-commission the machine, proceed as follows:
● Study the record made when the machine was decommissioned, and reverse the measures
that were taken for conservation and storage.
● Perform the measures listed in the "Commissioning" section.
See also
Commissioning (Page 69)
Decommissioning the machine (Page 80)
8.9
Faults
8.9.1
Inspections in the event of faults
Natural disasters or unusual operating conditions, such as overloading or short circuit, are
faults that overload the machine electrically or mechanically.
Operation
8.7 Decommissioning the machine
SIMOTICS HV C 1NB1402-2AA84-4CA0-Z
80
Operating Instructions 06/2018
Содержание 1NB1402-2AA84-4CA0-Z
Страница 2: ...26 06 2018 15 34 V3 00 ...
Страница 10: ...Table of contents SIMOTICS HV C 1NB1402 2AA84 4CA0 Z 10 Operating Instructions 06 2018 ...
Страница 22: ...Description SIMOTICS HV C 1NB1402 2AA84 4CA0 Z 22 Operating Instructions 06 2018 ...
Страница 84: ...Operation 8 9 Faults SIMOTICS HV C 1NB1402 2AA84 4CA0 Z 84 Operating Instructions 06 2018 ...
Страница 110: ...Disposal 11 4 Disposal of components SIMOTICS HV C 1NB1402 2AA84 4CA0 Z 110 Operating Instructions 06 2018 ...
Страница 112: ...Service and Support SIMOTICS HV C 1NB1402 2AA84 4CA0 Z 112 Operating Instructions 06 2018 ...
Страница 117: ...117 ...
Страница 118: ...118 ...
Страница 119: ...119 ...
Страница 120: ...120 ...
Страница 121: ...121 ...
Страница 122: ...122 ...
Страница 123: ...123 ...
Страница 124: ...124 ...
Страница 125: ...125 ...
Страница 126: ...126 ...
Страница 127: ...127 ...
Страница 128: ...128 ...
Страница 129: ...129 ...
Страница 130: ...130 ...
Страница 131: ...C 2 Declaration of conformity SIMOTICS HV C 1NB1402 2AA84 4CA0 Z Operating Instructions 06 2018 131 ...
Страница 132: ...Quality documents C 2 Declaration of conformity SIMOTICS HV C 1NB1402 2AA84 4CA0 Z 132 Operating Instructions 06 2018 ...
Страница 133: ...133 ...
Страница 148: ...148 ...
Страница 150: ...Additional documents SIMOTICS HV C 1NB1402 2AA84 4CA0 Z 150 Operating Instructions 06 2018 ...
Страница 154: ...Index SIMOTICS HV C 1NB1402 2AA84 4CA0 Z 154 Operating Instructions 06 2018 ...
Страница 155: ...AF Einbauerklärung Loher LDX U157 AJ EC Declaration of Conformity U161 ...