DECLARATION OF CONFORMITY
Sleipner Motor AS
P.O. Box 519, Arne Svendsensgt. 6-8
N-1612 Fredrikstad, Norway
Declare that this product with accompanying standard control systems complies with
the essential health and safety requirements according to:
DIRECTIVE 2013/53/EU
DIRECTIVE 2014/30/EU
DIRECTIVE 2014/35/EU
MC_0020
Bow Installation Instructions
Bow Installation Considerations and Precautions ..................... 3
Thruster Measurements ........................................................... 4
Thruster Specifications
.............................................................. 5
Technical Specifications
........................................................... 5
Control Box Technical Specifications
......................................... 6
Positioning the Stern Truster ..................................................... 7
Stern Thruster Cowls/ Grids ...................................................... 8
Positioning of the SX with Hydrodynamical Cover .................... 9
Thruster Installation Instructions
Thruster Installation Considerations and Precautions ............. 10
Grids or Cowls Assembly......................................................... 11
Tunnel Installation ................................................................... 12
Motor Installation ..................................................................... 13
Control Box Installation............................................................ 14
Thruster Electrical Installation ................................................. 15
Electrical Specifications
.......................................................... 16
Control Panel Cable Installation ............................................. 17
Visual Wiring Diagram ............................................................ 18
Control Panel Installation ........................................................ 19
Checklist for DC and IP Thrusters
...................................... 20
Spare Parts
............................................................................ 21
Warranty statement .............................................................. 21
Contents
EN
MC_0071
Installation Considerations and Precautions
EN
• Do not install the thruster in a position where you need to cut a stiff ener/ stringer/ support for the hull integrity without checking with the boat builder
this can be done safely.
• Contacts/ plugs or other joints in the control cables must be mounted so they will remain dry at all times.
• We advise painting the thruster with primer and antifouling.
(NB: Do not paint the anodes, sealings or propeller shafts)
• Do not fi nish the inside of the tunnel with a layer of gelcoat/ topcoat or similar. There is only room for a thin coat of primer and two layers of anti-fouling
between the tunnel and the props.
• keep installation within advised measurements. The entire surface is hard coated seawater resistant aluminium. Do not damage/penetrate the coat.
• The external stern thruster assembly and controller unit are ignition protected and can be installed in areas with the chance of explosive gases in
accordance to ISO 8846 and ABYC c1500. (Certifi cation pending)
• Ensure that the external stern thruster assembly does not disturb the water fl ow under the hull. At higher speeds, if the thruster is installed to
low it can cause damage to the thruster and/ or add additional drag and unwanted water splashing.
• The recommended minimum tunnel depth from the water surface is 140mm (5,51‘) to the centre of tunnel diameter. Place the Thruster as deep as
possible for better performance and reduced noise.
• When installing the thruster ensure it does not foul existing equipment inside the boat like motor bedding etc.
• If able ensure that sterndrives/ trimtabs do not interfere with the water fl ow from the thruster as this can reduce the thrust eff ectiveness considerably.
We recommend the use of our Side-Power cowls to enhance the performance and allow installation in shallow draft boats. Side-Power cowls will also
minimise the eff ect if sterndrives/ trimtabs obstruct the thruster.
• Ensure there is enough space both inside and outside the transom of the boat and the thruster does not get in confl ict with existing equipment
inside the boat like steerage links etc.
(NB: It is possible to mount the tunnel off set from the boat’s centre line if necessary.)
• Heat protection cut off is calculated from the thruster motor. To avoid cable overheating do not install place the volt cables from the thruster to the
control box near any heat sources.
It is the installers responsibility
When installing Side-Power equipment to follow the outlined regulations/ classifi cation rules (electrical/ mechanical) according to
international or special national regulations. Instructions in this guide cannot be guaranteed to comply with global electric/ mechanic
regulations/ classifi cation rules.
It is the installers responsibility
To follow all health and safety laws in accordance with their local outlined regulations/ classifi cation rules.
Before installation, it is important that the installer reads this guide to ensure necessary acquaintance with this product.
The recommendations made in this manual are guidelines ONLY, and Sleipner Motor AS (Side-Power) strongly recommend that
before installation, advice is obtained from a naval architect familiar with the particular vessel and regulations/ classifi cations.
This manual is intended to support educated/ experienced staff and is therefore not suffi cient in all details for professional
installation.
(NB: These instructions are only general instruction. If you are not skilled to do this work, please contact professional
installers for assistance.)
All electrical work must be done by a licensed professional.
IMPORTANT
Faulty installation of the tunnel, thruster or panel will render all warranty given by Sleipner Motor AS void.
MC_0038
Содержание SX-35/140
Страница 22: ...22 5630 6 2019 SX35 SX50 MC_0037 Notes EN ...
Страница 23: ...23 5630 6 2019 SX35 SX50 MC_0037 Notes EN ...