4  Determination of the position of installation 

To  reach  the  accuracy  specified  in  the  data  sheets,  the  sensor 
has  to  be  positioned  in  a  straight  conduit  and  at  a  place  with 
undisturbed  flow  profile.  An  undisturbed  flow  profile  can  be 
achieved if a sufficiently long distance in front of the sensor (run-in 
distance)  and  behind  the  sensor  (run-out  distance)  is  held 
absolutely  straight  and  without  disturbances  (such  as  edges, 
seams, bends, etc.). 

The  design  of  the  run-out  distance  is  also  important,  since 
disturbances do not only act 

in

 the direction of the air flow but also 

lead to turbulence 

opposite

 to the flow direction. 

 

 

run-in distance L1 

run-out distance L2 

 

 

Figure 1: Sensor position in the pipe 

 

L= total length of the measuring distance, L1 = length of the run-in 
distance, L2 = length of the run-out distance, D = diameter of the 
measuring distance 

The  sensor  tip  must  be  positioned  in  the  center  of  the  pipe 
opening as shown in Figure 1

The  following  table  shows  the  necessary  straight  conduit  lengths 
as a function of each disturbance. 

 

 

Содержание SS 20.60

Страница 1: ...SCHMIDT Flow Sensor SS 20 60 Instructions for Use ...

Страница 2: ...ormation 4 4 Determination of the position of installation 5 5 Mounting instructions 8 6 Electrical connections 9 7 Startup 10 7 1 LED display 10 7 2 Error signaling 12 8 Service information 13 9 Declaration of conformity 15 Imprint Copyright 2003 SCHMIDT Technology GmbH All rights reserved Printed in the Federal Republic of Germany Version 300754 02B ...

Страница 3: ...ity for a certain purpose and cannot be held liable for errors contained in these instructions for use or for accidental or sequential damage in connection with the delivery performance or use of this unit 2 Range of Applications The SCHMIDT flow sensor SS 20 60 is designed for stationary use in compressed air pipes air ducts or air shafts under atmospheric pressure conditions The sensor measures ...

Страница 4: ...d tightening torque 20 Nm minimum 30 Nm maximum 3 In case of mechanical strain vibration the nut AF24 must be secured additionally e g using a commercially available screw lock 4 Make sure to close the safety chain before pressure is applied The chain lock must be hung up in a way to avoid sagging of the chain ATTENTION The maximum allowed positive operating pressure of 16 bar must not be exceeded...

Страница 5: ...isturbances such as edges seams bends etc The design of the run out distance is also important since disturbances do not only act in the direction of the air flow but also lead to turbulence opposite to the flow direction run in distance L1 run out distance L2 D Figure 1 Sensor position in the pipe L total length of the measuring distance L1 length of the run in distance L2 length of the run out d...

Страница 6: ...s toward the measuring area 15 x D 5 x D Expansion conduit expands toward the measuring area 15 x D 5 x D 90 bend or T junction 15 x D 5 x D Two 90 bends in one plane 20 x D 5 x D Two 90 bends with 3 dimensional change in direction 35 x D 5 x D Shut off valve 45 x D 5 x D Table 1 Run in and run out distances This table lists the minimum values required in each case If the listed straight conduit l...

Страница 7: ...e 7 16 Installation position The sensor should preferably be installed in horizontally positioned pipes ATTENTION Avoid installing the sensor in a pipe with downward flow This would considerably increase the lower measuring range limit ...

Страница 8: ...ng the sensor in the pipe 2 Tighten the union nut AF24 until the arrow on the sensor housing corresponds to the direction of the pipe flow The angular deviation should not be greater than 3 referenced to the ideal position Otherwise the measurement accuracy may be affected You can check the set angular position by placing a bubble level on the stop face In case of wrong adjustment the through bolt...

Страница 9: ...2 bn sw bl 24 VDC Signal GND ws Digital Figure 3 SS 20 60 connection assignment view of the plug pins at the sensor The cable supplied has the following color assignment ws white bn brown sw black bl blue The negative of the dc voltage GND is at the same time the reference potential for the analog signal ATTENTION Only operate the sensor in the defined range of operating voltage 24 VDC 20 Undervol...

Страница 10: ...the signal outputs are specified on the rating plate see housing cover Note After applying the supply voltage the output signal will at first adopt a higher value and then level off at the correct measurement value after about 10 seconds 7 1 LED display The sensor has 4 LEDs indicating its current state ...

Страница 11: ...4 1 Ready for operation flow 5 2 Flow 5 3 Flow 20 4 Flow 50 5 Flow 80 6 Flow 100 overflow 7 Sensor element defective 8 Operating voltage too low 9 Operating voltage too high 10 Electronic temperature too high 11 Electronic temperature too low Table 2 Sensor state signaling LED off LED on green LED on orange LED flashes approx 2Hz red ...

Страница 12: ...acturer for repair The other error states signaled by the LEDs are not indicated at the analog output LED signaling remains active until the cause of the error has been eliminated ATTENTION Causes of any error signaling have to be eliminated immediately A significant exceeding or falling below the permitted operating parameters can result in permanent damage to the sensor ATTENTION During error st...

Страница 13: ...nated Cleaning the sensor tip The sensor tip can be cleaned to remove dust dirt by moving it carefully in warm water containing a washing up liquid if necessary a very soft brush can be used Before putting it back into operation wait until the sensor tip is completely dry ATTENTION Do not use strong cleaners solvents brush or other hard objects Recalibration If the customer has made no other provi...

Страница 14: ...t the manufacturer In case of defects the parts must be sent in to the supplier for repair When the sensor is used in systems important for operation we recommend keeping a replacement sensor in stock Test certificates Upon request we shall prepare at a charge a factory calibration certificate traceable to national standards ...

Страница 15: ...Instructions for Use SS 20 60 Page 15 16 9 Declaration of conformity ...

Страница 16: ...Instructions for Use SS 20 60 Page 16 16 SCHMIDT Technology GmbH Feldbergstrasse 1 D 78112 St Georgen Phone 49 0 7724 899 0 Fax 49 0 7724 899 101 info schmidttechnology de www schmidttechnology de ...

Отзывы: