!Maintenance!

1. 

It must be possible to turn the actuating shaft manually until the gripping eccentric engages and the  

 

safety gear switch must be actuated. When pulled out from the braking position, the actuating shaft  

 

(gripping eccentric) must turn back into neutral position.

2. 

The guide rails must only be oiled with specified lubricants. (Observe EC-type examination certificate). No  

 

greases, oils which become resinous etc.

3. 

Maintenance at least once annually (or operating hours or 

 contamination).
4. 

Avoid rust by cleaning and lubricating the moving parts.

5. 

6. 

7. 

Check the tractive force of the overspeed governor with required tractive force of the safety gear/safety  

 

module (at least statically).

Lubricate all joints, in particular the 
spring and the gripping eccentric (if 
they are not moving smoothly).

Schlosser 
Aufzugtechnologie GmbH
Felix-Wankel-Straße 4
85221 Dachau
T +49 8131 / 5186-0
www.schlosser.de

Ausgabe
edition

06.09.2018

Seiten
pages

2/7

Bearbeiter
person in charge

Kepplinger

Zeichnung Nr.
drawing nr.

5360.800.002

Combination KB55-EB75KS

General instructions

Front

Back

Lubricate between eccentric

and spring steel strip

Kingpin, can be pulled out

Kingpin, can be pulled out

It must be easy to move

the safety gear smoothly

on the kingpin.

6.

!Important!

Prior to commissioning:

1. 

Before commissioning and testing the guide rails must be cleaned thoroughly prior to installation!   

 

Whether „old“ or „new“, (due to dirt, old lubricant or protective agents in case of new rails!), they must  

 

be kept clean both before and after commissioning!!!

2. 

Should this not take place, negative changes in the braking force etc. can/will occur: In this case, any  

 

potential claim will be rejected. 

3. 

Should „old“ guide rails show very long skid marks or many and deep marks (e.g. from safety gear), they  

 

have to be replaced by new guide rails – of the same type.

4. 

After recommended test check (only functional test - low speed/empty lift car) a safety test (engagement  

 

test) must be carried out according to the applicable guidelines (e.g. EN 81-20/50), also for „SRMs“  

 

(conveyors), or according to the manufacturer‘s specifications.

 

Should none of the above provisions apply, the test must be executed in the „downward“ direction at  

 

least with nominal speed and nominal load without any braking of the drive unit (e.g. keep operational  

 

brake open!), otherwise no performance record! In the event of uncertainties, please contact us - as  

 

manufacturer - immediately.

 

Periodical tests (engagement tests) must also be carried out

 

at regular intervals.

 
5. 

The brake power is assessed by persons with professional

 

expertise (e.g. inspection bodies etc.).

It must be possible to move the safety gear/safety module 
smoothly on the kingpin (floating system).

Содержание KB55-EB75KS EU-SG 333

Страница 1: ...he overspeed governor incl UCM A3 General instructions 5360 800 002 Mounting adjustment 5360 800 003 Mounting adjustment check 5360 800 004 Mounting information 5360 800 005 Check 5360 800 006 Test instructions information 5360 800 007 Kingpin can be pulled out Brake shoe retainer Brake shoe Brake pads Release slider Lockwash Double eccentric Kingpin can be pulled out Spring steel strip inside Rel...

Страница 2: ... kingpin 6 Important Prior to commissioning 1 Before commissioning and testing the guide rails must be cleaned thoroughly prior to installation Whether old or new due to dirt old lubricant or protective agents in case of new rails they must be kept clean both before and after commissioning 2 Should this not take place negative changes in the braking force etc can will occur In this case any potent...

Страница 3: ...ic 8 ca 1 00 2 00mm min 0 5 S je A Angle joint 14 Spindle for adjusting M10 15 Freewheel yoke 16 Reset cam 19 Reversing lever 17 opt double reset clamp High speed Adjustment Turn the thread M10 15 with the angle joint 14 until the length to the release slider 5 in adjusted in the open position both sides Safety gear KB 55 Adjustment of the set screws M8 a Press the release slider 5 up until the br...

Страница 4: ...s 1 opposite the Actuation lever 22 is an advantage 2 Check type EB 75 KS for synchronous running l Press down brake upwards the actuating lever 22 until both double eccentrics 8 are pressed onto the guide rails Check If not Change clearance 1 2 mm between brake shoe 10 and guide rail slightly by adjusting the adjusting screw M6 Note A test run provides clarity Slow raising of the system test run ...

Страница 5: ... the guide rail by loading activity or one sided loading of the lift This is because the later enlargement of the clearance is often not possible EB75KS EU SG 313 Date UCM NL12 400 1002 169 04 Rev 1 Serial No Tripping spd max m s Brake force 25490 29399N Guide head Aufzugtechnologie G Schlosser GmbH Felix Wankel Str 4 85221 Dachau Switching cam 21 Positioner sleeve Safety switch 27 Freewheel switc...

Страница 6: ...rmal operation of the lift If necessary brake shoes can be replaced Visual examination is considered sufficient The objective of the test prior to commissioning is to determine the proper as sembly the correct adjustment and the strength of the functional unit comprising the car safety gear guide rails rail mountings Tripping engagement forces At least double the required pull in force lk of the s...

Страница 7: ... Straße 4 85221 Dachau T 49 8131 5186 0 www schlosser de Ausgabe edition 06 09 2018 Seiten pages 7 7 Bearbeiter person in charge Kepplinger Zeichnung Nr drawing nr 5360 800 007 Note 1 In the case of weightless testing downwards electronic test device the bouncing of the cabin can cause the brake to fall back or be pulled into the upwards braking position Bouncing counterweight 2 Also a release fro...

Страница 8: ...5 EB75KS Schlosser Aufzugtechnologie GmbH Felix Wankel Straße 4 85221 Dachau T 49 8131 5186 0 www schlosser de Ausgabe edition 06 09 2018 Seiten pages 1 Bearbeiter person in charge Kepplinger Zeichnung Nr drawing nr 5360 800 010 Starting condition Final Detail release lever actuating bar Half nut M12 Half nut M12 Disk Rubber ring 6KT screw M12x40 Option high speed Alternativ detachable outer housi...

Отзывы: